Hello!
We are renovating a single-family house and improving its energy efficiency. The whole project has been running with an architect since January 2024. At the beginning, everything went to our complete satisfaction; for example, he succeeded very well in implementing our ideas in the drafts for the renovation.
However, we now have the impression that progress is becoming increasingly sluggish. Of course, one can read exactly in the HOAI what the basic services of each phase are. But which of these are actually visible to the client? We have the impression that the entire process has been very non-transparent so far. Therefore, I would appreciate assessments on whether everything is still within the normal range or if we need to take a stricter look?
The architect carried out the preliminary investigation and basic design free of charge in advance; we then concluded the architect contract over service phases 3 and 5 to 8. Based on the cost estimate from service phase 2, a fixed price of €29,125 net was agreed upon, regardless of how the actual construction costs develop.
So far, we have received partial invoices at irregular intervals. Including the last invoice, we have thus paid 100% of service phase 3 (design planning), 80% of service phase 5 (execution planning), and 30% of service phase 6 (preparation of awarding contracts).
What especially puzzles us is that despite repeated inquiries, we still do not have a cost calculation, which should actually be an integral part of service phase 3. The reasons he gave for the absence of a cost calculation were varied, e.g., still missing offers from craftsmen or because we had not yet decided how much tiling we want. Besides the cost calculation, a construction schedule is also missing.
Here is a list of the services provided so far, as far as visible to us:
- Cost estimate from service phase 2 (at the second level of the cost breakdown, status: February 2024)
- Floor plans (ground floor, upper floor, section, system section) - scale 1:50
- Foundation plan 1:50
- Roof floor plan (1:50) with section (1:20) and system diagram
- Elevations east/west, north/south (1:50)
- Calculation of living and usable areas
- Sanitary planning (1:50)
- List of existing windows
- Specification of windows constructions
From his reports, I know that he has obtained quotations from two roofers and two window manufacturers. Inquiries for the other trades are apparently still ongoing. He assured me that excavation work (for the foundation insulation) and demolition work can begin in early August. But I have not yet seen any offers or even contracts for this.
Are we moving within the usual range with the services provided so far? Or is there cause for concern?
We are renovating a single-family house and improving its energy efficiency. The whole project has been running with an architect since January 2024. At the beginning, everything went to our complete satisfaction; for example, he succeeded very well in implementing our ideas in the drafts for the renovation.
However, we now have the impression that progress is becoming increasingly sluggish. Of course, one can read exactly in the HOAI what the basic services of each phase are. But which of these are actually visible to the client? We have the impression that the entire process has been very non-transparent so far. Therefore, I would appreciate assessments on whether everything is still within the normal range or if we need to take a stricter look?
The architect carried out the preliminary investigation and basic design free of charge in advance; we then concluded the architect contract over service phases 3 and 5 to 8. Based on the cost estimate from service phase 2, a fixed price of €29,125 net was agreed upon, regardless of how the actual construction costs develop.
So far, we have received partial invoices at irregular intervals. Including the last invoice, we have thus paid 100% of service phase 3 (design planning), 80% of service phase 5 (execution planning), and 30% of service phase 6 (preparation of awarding contracts).
What especially puzzles us is that despite repeated inquiries, we still do not have a cost calculation, which should actually be an integral part of service phase 3. The reasons he gave for the absence of a cost calculation were varied, e.g., still missing offers from craftsmen or because we had not yet decided how much tiling we want. Besides the cost calculation, a construction schedule is also missing.
Here is a list of the services provided so far, as far as visible to us:
- Cost estimate from service phase 2 (at the second level of the cost breakdown, status: February 2024)
- Floor plans (ground floor, upper floor, section, system section) - scale 1:50
- Foundation plan 1:50
- Roof floor plan (1:50) with section (1:20) and system diagram
- Elevations east/west, north/south (1:50)
- Calculation of living and usable areas
- Sanitary planning (1:50)
- List of existing windows
- Specification of windows constructions
From his reports, I know that he has obtained quotations from two roofers and two window manufacturers. Inquiries for the other trades are apparently still ongoing. He assured me that excavation work (for the foundation insulation) and demolition work can begin in early August. But I have not yet seen any offers or even contracts for this.
Are we moving within the usual range with the services provided so far? Or is there cause for concern?