Bauexperte
2016-10-24 10:05:58
- #1
Hello,
Bare shell or with windows + roof?
The conventional, i.e. commercial, finishing of a single-family house of 140 sqm takes about 3 months. The trades build upon each other; craftsmen are on the construction site for several hours daily.
If your friends/acquaintances agree to help in the evenings (it gets dark early) and on weekends – and do so reliably, it certainly won’t be done in less than 6 months, and I still consider that optimistic.
*Agreeing to help* is something different from working permanently on interior finishing; especially if your own self-employment must secure your livelihood – maybe also that of employees!
Rhenish greetings
I wanted to have a shell construction built for about 100,000 €.
Bare shell or with windows + roof?
I wanted to do the interior finishing completely by myself.
Or rather with friends who have a painting or sanitary company.
Electricians, locksmiths, etc. are also available or have agreed to help.
By help I mean that they help several days a week in the evenings or during the day.
I have planned about 3-4 months until the interior finishing is complete.
The conventional, i.e. commercial, finishing of a single-family house of 140 sqm takes about 3 months. The trades build upon each other; craftsmen are on the construction site for several hours daily.
If your friends/acquaintances agree to help in the evenings (it gets dark early) and on weekends – and do so reliably, it certainly won’t be done in less than 6 months, and I still consider that optimistic.
*Agreeing to help* is something different from working permanently on interior finishing; especially if your own self-employment must secure your livelihood – maybe also that of employees!
Rhenish greetings