Fleckenzwerg
2022-09-19 08:35:27
- #1
Good morning,
we are actually on the home stretch with our house construction with the general contractor actually. The building is enclosed, but because of a construction door in the side entrance, it is not yet sealed; everything outside is finished. The electrical rough-in has been installed, plaster is on the interior walls, at the end of the week the screed will be poured – it will be dried with the help of the Hotboy. Shortly before that, the house connections will be made. A big question mark is the heat pump. According to our information, it was only ordered in late summer. The heating installer is not giving a clear statement. He only says that it is supposed to be installed in November anyway (after the tiles), so there is no need to worry about delivery time. The general contractor is also very relaxed about it. Now the question. What should we expect if the heat pump – oh surprise! – does not arrive and the delivery date is postponed far into the future, possibly even into next spring, as with many others? What does that mean for the building structure? Does the construction need to be kept at a certain minimum temperature over the winter? Does moisture need to be monitored? What about painting, wallpapering, installation of the kitchen – all planned for November. That is quite a chain of consequences that might come with it and for which a plan B should be considered. For example, the kitchen installer has already indicated that he cannot store the furniture and appliances indefinitely. We want to address all these questions promptly in a discussion with the general contractor. What is the forum’s opinion on this, and are there any other questions we should ask?
we are actually on the home stretch with our house construction with the general contractor actually. The building is enclosed, but because of a construction door in the side entrance, it is not yet sealed; everything outside is finished. The electrical rough-in has been installed, plaster is on the interior walls, at the end of the week the screed will be poured – it will be dried with the help of the Hotboy. Shortly before that, the house connections will be made. A big question mark is the heat pump. According to our information, it was only ordered in late summer. The heating installer is not giving a clear statement. He only says that it is supposed to be installed in November anyway (after the tiles), so there is no need to worry about delivery time. The general contractor is also very relaxed about it. Now the question. What should we expect if the heat pump – oh surprise! – does not arrive and the delivery date is postponed far into the future, possibly even into next spring, as with many others? What does that mean for the building structure? Does the construction need to be kept at a certain minimum temperature over the winter? Does moisture need to be monitored? What about painting, wallpapering, installation of the kitchen – all planned for November. That is quite a chain of consequences that might come with it and for which a plan B should be considered. For example, the kitchen installer has already indicated that he cannot store the furniture and appliances indefinitely. We want to address all these questions promptly in a discussion with the general contractor. What is the forum’s opinion on this, and are there any other questions we should ask?