When to apply for electricity grid connection?

  • Erstellt am 2014-04-16 08:23:29

Masipulami

2014-04-16 08:23:29
  • #1
Good morning everyone,

we will soon begin the earthworks for the foundation slab.

Now I am wondering when is the right time to submit the order for the electricity network connection to the local utility provider?

Can I submit the application now and then arrange a specific appointment as soon as the house reaches a certain state X?

We are building without a basement, meaning the line will be laid from the street to the utility room.

How was it for you specifically? At what point was the application submitted and when was the house connection ultimately installed?

Thank you very much in advance for your feedback.
 

klblb

2014-04-16 08:57:47
  • #2
1. Obtain an offer from the local supplier
2. Accept or commission the offer
3. Make an appointment for the installation of the electricity grid connection
4. Your supplier will handle the electricity grid connection, the construction site power box must be provided by your electrician/contractor
5. Later, the construction site power box will be dismantled and relocated to the utility room

You clarify the details with your supplier.

And the whole process should happen quickly! Electricity will be needed at the latest when the foundation slab is laid. Water as well. And toilet etc.
 

projekthausbau

2014-04-16 09:25:43
  • #3
"...Now the question arises for me when the right time is to submit the order for the installation of the electricity grid connection to the local supplier?

Can I already submit the application now and then arrange a specific date once the house has reached condition X?..."

... In any case, submit the application to the supplier so that it is processed in time. Surely, you will not be the only ones currently building a house. Therefore, the suppliers will have a lot to do.
 

Masipulami

2014-04-16 09:41:11
  • #4
Thank you for your feedback.

The offer and application from the supplier have been with me since yesterday. I now have to fill them out, include the site plan and cadastral excerpt, and send them back.

So do I understand correctly that the network connection must already be established for the construction power meter box?

The application will then be sent by mail today.
 

Wastl

2014-04-16 09:58:01
  • #5
The earlier the better. With us, we had to wait almost 3 months. In addition, first the wastewater, then the water, and only afterwards could the electricity be done. When the electricity was finally up, the scaffolding was in place for plastering, and they couldn't dig the trench for the electrical connection,....
 

Masipulami

2014-04-16 10:01:16
  • #6
You had to wait 3 months for the construction power? Or for the final house connection?
 

Similar topics
15.02.2011Building permit application12
21.10.2011Floor slab insulation "Yes!" or "No!"14
18.09.2012Construction of a base slab with frost skirt but without foundation10
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
14.09.2012House financing - house, garage, and foundation slab approx. 290,000 EUR11
26.10.2012External perimeter insulation floor slab, basement mold risk11
21.11.2013Is the floor slab still possible this year?15
15.07.2014Foundation slab for Danwood bungalow? Company for complete works?11
02.01.2015No construction power box, take electricity from the neighbor18
04.09.2015Electricity connection to supplier Süwag10
06.11.2018House connection: Telekom does not want to drill through the white tank17
10.04.2020Costs and Planning of House Connection29
17.09.2020House connection pillar in the garden vs. house connection directly in the utility room35
30.12.2020Current processing time for construction financing applications at banks69
14.04.2021Planning HAR/Utility Room - Technical plans unknown12
08.10.2022Requirements for construction power box Construction power distributor12
03.12.2024Wibank Hessen Loan Application Documents and Experiences55
25.09.2023The supplier has incorrect meter numbers in the system - what to do?42
19.07.2024Application KfW 442 Solar Power for Electric Cars42

Oben