Hello, due to a very current issue: I have often read something in the forum on this topic, but unfortunately cannot find anything concrete through the search right now. How "uneven" is cement screed normally allowed to be to be accepted by us. The tiler (commissioned by us) has already indicated: leveling compound will be necessary, also due to the large-format 1.20m tiles. With a 3m straightedge I measure "up to" 5...6mm height difference. With a shorter straightedge (e.g. 2m) correspondingly less, it’s only about a few small bumps. It also has nothing to do with drying, the screed has been in place for 2 weeks and the bumps were there from the beginning and have neither improved nor worsened.