Time delay due to plumber. What can I do?

  • Erstellt am 2014-02-14 12:19:13

Bata

2014-02-14 12:19:13
  • #1
Hello,

we are building a single-family house with a developer; we specifically chose a developer so that we wouldn’t have to organize so much ourselves. When selecting the craftsmen for the individual trades, we named the developer who and which ones he would take on. In particular, the plumber, who is also responsible for the heat pump and underfloor heating, was selected and commissioned by the developer.

Construction began for us at the end of August. Before Christmas, the roof was on and the wet plastering work inside the house was finished.
Then there was a pause of 3.5 weeks, which is understandable because of Christmas, everyone has time off then.

Now our problem.

Since the plumber has been on site, he has only done things half-heartedly. Before the plastering work, he did not manage to lay all the water pipes under plaster. The foreman’s statement was that we would open it up again later. (At first, not my problem, I thought because I have a fixed price.) Now the plumber is there and is laying the remaining water pipes and the ventilation system; unfortunately, he has been doing this for over 2 weeks, and this is my problem.

Either only one technician comes and works, or no one comes at all! And then there is a 2-day construction stop again.

When I ask the boss of the plumbing company, he always says his guys are sick, he doesn’t know how he will manage it, etc. Apparently, they do all of the developer’s constructions as a reference. And then he tells me our construction is already so far along that it isn’t so bad. (Normally, the construction manager would take care of this, but he doesn’t.) Unfortunately, we did not agree on any schedule or completion date for the construction because the developer comes from the neighboring town, and you always want to believe in the best. (I know, someone will probably say it’s our own fault, but that doesn’t help me now.) I cannot get an appointment with my construction manager on site (he doesn’t even answer his phone) to clarify the matter, and when the construction manager does give dates over the phone, they are wrong anyway. (Unfortunately, I’ve already been through all this; so far, I’ve had to call after every trade to check if the dates are correct.)

Can someone give me a tip on how I can proceed? Or what I can do? I don’t want to threaten with a lawyer.
 

nordanney

2014-02-14 12:50:54
  • #2
Without written fixed dates, you have bad odds. Why didn’t you at least agree on a completion date? Even if nothing else happens in the next six months, you can’t do anything. So keep "bothering" the craftsman until he has delivered his service ;)
 

ypg

2014-02-14 14:18:06
  • #3
As you understand it, you are not the builder at all. You are buying a finished house - do you have any rights there?
 

Bata

2014-02-14 14:25:03
  • #4



We are building
Excerpts from the construction description "TURNKEY":
 

ypg

2014-02-14 15:14:14
  • #5


Well then :) ... Then it is not a property developer, but a general contractor (GU/GÜ), so incorrectly posted in your opening sentence. That makes THE difference and I refer to nordanney's answer :)
 

Der Da

2014-02-17 13:45:30
  • #6
Who is the contracting party? The plumber or the house company. Maybe they can put more pressure on. But when it comes to illness, probably no one can do anything... and since you have no guarantees, you just have to take it as it comes.
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
26.09.2011Finding tiles from other manufacturers / sample selection for builders13
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
16.07.2012The builder "outsources" fixed-price services to subcontractors12
03.08.2012Contract Supplement to the Construction Contract by the Developer36
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
18.02.2014Massive problems with the builder - is contract termination possible?33
23.06.2014Developer charges heavily for replanning - justified?12
08.10.2014How do you search for a suitable property developer?30
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
01.03.2015The developer does not build according to the plan14
15.04.2015Duplex construction: Joint or separate developer?20
30.08.2019Is it sensible to have a building surveyor for condominiums from the developer?11
31.05.2019The construction manager does not come, does not check, or he doesn't care about anything16
15.09.2019Developer refuses to hand over documents32
09.02.2020Developer | Special Request | Cost Assumption38
16.05.2021Approach for Initial Contact with Property Developers & Prefabricated Building Suppliers24

Oben