barcuda
2012-10-07 19:53:36
- #1
Dear builders and those who want to become builders,
I would like to take a question from a user as an opportunity to point out the subtleties – or rather possible fine points – in contract drafting. In the specific case, the builders were informed during planning that the finished floor on the ground floor must be at least 35 cm above ground level to avoid possible construction damage due to moisture. The result could be that the users then accept steps to the house that they actually did not want, or have to bear additional costs for a sealing that was initially not contractually agreed upon.
This is a "classic" surprise in the planning or construction phase. As a rule, a construction contract is signed with a general contractor – hereafter simply called GU – before the planning, so the height alignment of the house is not precisely defined. In the contract, the GU describes his conditions on which the contract price is based. The topic of height alignment is usually only briefly and curtly mentioned, for example that the finished floor lies 30 cm above ground level. Sounds logical, after all, we know that it is good if the water flows away from the house. Sometimes one or another builder assumes this will be compensated with the outdoor facilities in order to have as level a transition to the garden as possible.
Possible results of the initially described case could be:
- the users accept steps to the house that they actually did not want
- additional costs (change orders) arise for sealing that was not contractually agreed upon
- the builders fill the ground after completion to such an extent that the height difference described as a condition by the GU is no longer maintained – if moisture damage then occurs, the builders are to blame.
None of these results is satisfactory, although the GU can be accused of insufficient clarification, legally the GU is on safe ground.
The example described above is just one of many traps hidden in the seemingly harmless wording of construction contracts and their building descriptions. Even more difficult to assess than the small print is what is not printed.
Please forgive me for advocating – as a professional construction supervisor – that an external expert consultation be obtained before signing the contract. However, the greatest potential savings in expenses and trouble lie precisely in the phase before the contract.
I would like to take a question from a user as an opportunity to point out the subtleties – or rather possible fine points – in contract drafting. In the specific case, the builders were informed during planning that the finished floor on the ground floor must be at least 35 cm above ground level to avoid possible construction damage due to moisture. The result could be that the users then accept steps to the house that they actually did not want, or have to bear additional costs for a sealing that was initially not contractually agreed upon.
This is a "classic" surprise in the planning or construction phase. As a rule, a construction contract is signed with a general contractor – hereafter simply called GU – before the planning, so the height alignment of the house is not precisely defined. In the contract, the GU describes his conditions on which the contract price is based. The topic of height alignment is usually only briefly and curtly mentioned, for example that the finished floor lies 30 cm above ground level. Sounds logical, after all, we know that it is good if the water flows away from the house. Sometimes one or another builder assumes this will be compensated with the outdoor facilities in order to have as level a transition to the garden as possible.
Possible results of the initially described case could be:
- the users accept steps to the house that they actually did not want
- additional costs (change orders) arise for sealing that was not contractually agreed upon
- the builders fill the ground after completion to such an extent that the height difference described as a condition by the GU is no longer maintained – if moisture damage then occurs, the builders are to blame.
None of these results is satisfactory, although the GU can be accused of insufficient clarification, legally the GU is on safe ground.
The example described above is just one of many traps hidden in the seemingly harmless wording of construction contracts and their building descriptions. Even more difficult to assess than the small print is what is not printed.
Please forgive me for advocating – as a professional construction supervisor – that an external expert consultation be obtained before signing the contract. However, the greatest potential savings in expenses and trouble lie precisely in the phase before the contract.