Hello,

I am currently in the process of requesting construction power and unfortunately have no idea what the rental cost of a construction power distributor should be. Of course, the electricity is charged on top, but surely no one is supposed to make a profit from that, right?

What is the rental cost for such a construction power distributor? Required are 380 V and 32 A.

Thanks for your answers
 

ypg

2017-10-17 18:54:01
  • #2
The rent is flat rate for, let's say, 6 months including the setup, then about €30/month. I think the setup cost around 400. Construction electricity itself is much more expensive than household electricity, I believe we paid about 200? We connected the dehumidifiers at the neighbors’, and the construction supervisor also took over the consumption there. Oh, by the way, with us too.
 

RobsonMKK

2017-10-17 19:39:54
  • #3
Box for the construction period approx. 700€ Connection by the municipal utilities 250€ What will come in the end, we shall see.
 

winnetou78

2017-10-17 19:49:41
  • #4
And again I have to say, regionally different.

Provide construction site power box with delivery and pickup 150 euros,
rental per day 1.50,
install meter from municipal utilities 49 euros,
 

RobsonMKK

2017-10-17 20:00:57
  • #5
I fully agree with the Indian.
 

winnetou78

2017-10-17 20:10:53
  • #6
That is bordering on a miracle [emoji6]
 

Similar topics
06.12.2017Until when must construction power be taken?22
05.07.2018Temporary electricity stolen - amount of compensation?17
20.07.2018Construction power or house connection? How much construction power is needed?12
13.11.2018Grandma's house | Right of residence | Rent by oneself15
19.03.2019Construction power is being connected. Does the builder have to be present?10
04.10.2019Easily switch temporary power provider?21
10.01.2022Determine construction power costs / eOn charges too much36
09.10.2024Construction electricity/construction water costs are the responsibility of the builder11

Oben