Hello everyone,

we want to build this year and already knew when buying the plot that it would probably come down to a pile foundation.
However, we want to have a soil survey done in advance and have received the first offer. Instead of about €1,500, we are supposed to pay about €3,000 for it.
This difference is explained by a peat content in the soil, as we already have an initial survey up to 5 meters deep. A pressure sounding would have to be carried out.
In the quotation from the pile foundation company, the pressure sounding is estimated at €975 net.

Has anyone perhaps had a soil survey by pressure sounding (with regard to a deep foundation) done for their house construction who can give us a price?

There will certainly be many more questions to follow and I hope to find people here who can contribute good ideas or share experiences.

Regards
 

Bauexperte

2015-04-01 10:13:56
  • #2
Hello,


Experiences of third parties don't matter; what is important is what is stated in your contract! The company you commissioned will hardly orient itself to the competition in such a way that it possibly grants a discount ;)

Check your contract with the commissioned company and if you don’t trust yourself to do so – which would not be unusual – have a lawyer look at it. Only in this way will you make progress; if at all, a subsequent reduction of the agreed amount is possible through the contract itself.

Rhineland regards
 

Griesi

2015-04-01 10:26:38
  • #3
um, thanks for the quick response.

I have not signed any contract yet, these are just preliminary offers.. the piling company made the offer with regard to several already piled neighboring plots.

But if it turns out that it is €3,800 extra for an independent soil survey, I will commission the company directly for piling, since the soil survey costs only €975 net there.

I was hoping that someone here could tell me why the offer for the soil survey suddenly amounts to €3,800 and not around €1,500, as the house building companies have independently indicated to me.

Best regards
 

Griesi

2015-04-01 10:27:41
  • #4
3,800€ I obviously mean o_O
 

Similar topics
15.01.2013Soil survey report for house construction10
09.09.2013Costs for soil replacement, soil survey for construction ground, clayey25
16.04.2014Cost of soil survey - Does the architect pay or do we?12
24.07.2014Soil assessment report, filling - additional costs?11
23.11.2014Soil report shocked us!!34
09.04.2015Ground too soft - drilling / soil survey not possible12
17.03.2015Soil survey in the Hannover area. Costs? Providers?10
03.09.2015Soil survey before purchasing property - who does it?14
26.11.2015Soil assessment - Threshold values for arsenic and heavy metals19
13.02.2017Soil survey before purchasing property?20
10.08.2016Soil report - silty and artificial fill11
17.10.2019Costs of soil assessment / geotechnical investigations34
27.03.2017Approximate costs for earth excavation based on soil investigation14
26.03.2018Is a soil report not possible before surveying the new construction area?16
08.05.2018Is a soil survey necessary? Better for cost estimation?17
12.12.2018Soil report prepared without my knowledge16
13.06.2019We need an additional soil report11
19.11.2019Preliminary contract for land due to soil survey17
25.02.2020What should we pay attention to in the soil report?21
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33

Oben