Sloping plot. Planned a bungalow with a double garage.

  • Erstellt am 2017-02-01 12:20:46

2000youandme

2017-02-01 12:20:46
  • #1
Hello forum members,

I own a sloped plot and plan to build a bungalow with a double garage on it.
The construction contract has already been signed with a construction company.
In the contract documents, the double garage is directly attached to the house, and the contract states: "The bungalow will be founded with a base slab on strip foundations or approximately 80 cm gravel cushion foundation to compensate for the slope."
Now the plot has been leveled. The slope is approximately 2 m in total. Afterwards, I received a new drawing in which the garage is separated from the bungalow, a corridor is drawn between the garage and the house, and then the house is drawn further down. I then informed the construction company that I want the original version as planned from the beginning, where the garage and the bungalow are connected and at the same level. However, the company did not like that at all. Now I am receiving an order letter for "175 cbm crushed stone base layer under the base with compactable material additionally installed as slope compensation" and a gross price of 7,392 euros which I am supposed to sign.

Do I have to bear the costs for the gravel?

In the contract, the drawing shows the garage attached to the house and the plot has always had this slope. Approximately 80 cm is an approximate figure and does not mean up to a maximum of 80 cm, does it? I told the company from the start that the plot has a slope of about 2 meters.

I would very much appreciate your opinions.

Best regards
 

Peanuts74

2017-02-01 12:27:26
  • #2
Ah, did it work
Did the general contractor not inspect the property?
 

ypg

2017-02-01 12:55:14
  • #3
Basically, it can happen that the earthworks have to be carried out more extensively than stated and signed in the contract. Of course, then additional services in the item earthworks are added, which must be paid by the client on site, even if the client is the ordering party under the contract with the GU. That is why one should also keep a generous buffer for the earthworks, especially in the case of a hillside location.

In brief, regards
 

Nordlys

2017-02-01 13:12:46
  • #4
I understand it like this. In the construction description, he offered 80cm gravel bedding and calculated accordingly. Now he realizes he needs significantly more. It's steeper. He is trying to salvage something. If we take the garage forward, the house backward, then I roughly get by with the calculated amount of gravel. You now: I don't want that. He now: then it costs more. Don't you talk to each other?
 

Peanuts74

2017-02-01 13:20:12
  • #5
So the question would be what the contract says about earthworks. In general, however, the BU cannot change the plan in such a way that the originally connected house and garage, possibly still with a passage, suddenly become completely separate. However, the price seems generally reasonable to me, after all it is about approx. 300 tons of gravel plus installation.
 

2000youandme

2017-02-01 17:10:39
  • #6
The general contractor did not view the property beforehand. However, he has known about the 2-meter slope since the first meeting. We even discussed it on the day of the contract signing. His employee told me on the phone that the reason for the new variant was that it would not look good if the house was built so high, as it would then appear to be hanging in the air. I then told her that, unfortunately, I could not share that opinion and would prefer the first variant as planned. After that, I spoke with the general contractor. He said that with the first variant "little fences and walls" would be needed to support the whole thing and that, from his side, the gravel (at his expense) would not be a big problem for him. He then wanted to send me a cost breakdown of the additional expenses, and now I am receiving an order form for gravel that I am supposed to pay for. Therefore, I have now turned to you because I would like to know whether I have to pay for the gravel that is needed for this house construction and is also part of the contract. The contract states "approx. 80 cm", not maximum. And the general contractor has known from the beginning about the 2-meter slope.
 

Similar topics
17.04.2016Value of land and bungalow B5511
13.09.2012Feeling pressured into a contract, is that normal?17
08.06.2018130 m² bungalow with double carport on a 600 m² plot?64
16.03.2018Old building on property - Bungalow extension - Various problems10
16.12.2018Floor plan design single-family house (city villa 140 sqm) on a slope with double garage495
30.07.2019130 sqm L-shaped bungalow including double garage35
16.10.2019Bungalow - does it make sense on a plot like this?21
02.11.2019Assess slope45
01.05.2020Plot with slope - New development area18
04.05.2020Assessment of land - hillside location15
26.03.2021Floor plan of a bungalow on already used land108
12.05.2021Property on a slope, is the purchase worthwhile?29
22.01.2022Construction costs for a turnkey single-family house on a slope 202219
19.12.2022Floor plan help needed for bungalow33
30.08.2023Preparing the site for the floor slab on a slight slope15
23.12.2023Floor plan of a two-story house with a slight slope61
30.09.2024Floor plan bungalow 125 sqm conical plot39
17.09.2024New development area - sloping plot19
07.02.2025Cost issue for earthworks on a slope22
10.05.2025Which property would you choose? Single-family home with double garage44

Oben