2000youandme
2017-02-01 12:20:46
- #1
Hello forum members,
I own a sloped plot and plan to build a bungalow with a double garage on it.
The construction contract has already been signed with a construction company.
In the contract documents, the double garage is directly attached to the house, and the contract states: "The bungalow will be founded with a base slab on strip foundations or approximately 80 cm gravel cushion foundation to compensate for the slope."
Now the plot has been leveled. The slope is approximately 2 m in total. Afterwards, I received a new drawing in which the garage is separated from the bungalow, a corridor is drawn between the garage and the house, and then the house is drawn further down. I then informed the construction company that I want the original version as planned from the beginning, where the garage and the bungalow are connected and at the same level. However, the company did not like that at all. Now I am receiving an order letter for "175 cbm crushed stone base layer under the base with compactable material additionally installed as slope compensation" and a gross price of 7,392 euros which I am supposed to sign.
Do I have to bear the costs for the gravel?
In the contract, the drawing shows the garage attached to the house and the plot has always had this slope. Approximately 80 cm is an approximate figure and does not mean up to a maximum of 80 cm, does it? I told the company from the start that the plot has a slope of about 2 meters.
I would very much appreciate your opinions.
Best regards
I own a sloped plot and plan to build a bungalow with a double garage on it.
The construction contract has already been signed with a construction company.
In the contract documents, the double garage is directly attached to the house, and the contract states: "The bungalow will be founded with a base slab on strip foundations or approximately 80 cm gravel cushion foundation to compensate for the slope."
Now the plot has been leveled. The slope is approximately 2 m in total. Afterwards, I received a new drawing in which the garage is separated from the bungalow, a corridor is drawn between the garage and the house, and then the house is drawn further down. I then informed the construction company that I want the original version as planned from the beginning, where the garage and the bungalow are connected and at the same level. However, the company did not like that at all. Now I am receiving an order letter for "175 cbm crushed stone base layer under the base with compactable material additionally installed as slope compensation" and a gross price of 7,392 euros which I am supposed to sign.
Do I have to bear the costs for the gravel?
In the contract, the drawing shows the garage attached to the house and the plot has always had this slope. Approximately 80 cm is an approximate figure and does not mean up to a maximum of 80 cm, does it? I told the company from the start that the plot has a slope of about 2 meters.
I would very much appreciate your opinions.
Best regards