Hello everyone,

based on preliminary sketches that we have already sent to the prefabricated house manufacturer, he has prepared an offer for us. After being on site today, I was a bit shocked when I saw the total costs.

Could you maybe help me and evaluate whether this roughly makes sense?

I deliberately provided the information beforehand that we have reserved a plot of land with the following details:


Plot size:605 m²
Purchase price:Included in the purchase price are:
the price for the land,
the street connection fee,
the sewage fee,
the sewage treatment fee,
the water supply fee,
the surveying costs in the current condition, as well as the costs for establishing the sewage and water connection up to the building plot.

(all information is non-binding and without guarantee)

Price per square meter:90.00 euros


Purely mathematically, the plot itself comes to 54,450.00 EUR. Including notary costs, etc., I roughly calculated 60,000.00€ for the plot.

What was then added in the ancillary building costs surprised me a bit. Can it all be correct? A total of 94,059.27€? This is a new development area.

I am aware that this is only a preliminary offer so we can estimate what amount to expect. The 180 m² living space is a bit much, about 150 m² will suffice for us. This concerns a city villa; I don’t want to discuss the sketches themselves for now. I will inquire elsewhere with these sketches so that everyone has the same requirements. It is clear that a lot will still change.

I think the price for the house itself roughly fits. Approximately 1777€ / m² are charged for the house alone.

I hope it is okay that I post the offer here. I tried to remove all unnecessary data.

Thanks in advance for your support.

Best regards, Ravosch
 

EveundGerd

2016-04-30 23:52:44
  • #2
I don't see anything in this “offer” that I would sign. Where is the construction performance description for this offer? The listed incidental costs are not fixed. The provider points out that it is up to you to determine the exact incidental costs. Don’t let yourselves be driven crazy by this promotional period or these credits. In my opinion, this is just window dressing. The potential customer is being pressured in this way! Paying the invoice before service delivery in order to deduct a discount? Very questionable method. Please get some more offers and keep in mind that a prefabricated house is often more expensive than a monolithically built one.
 

b54

2016-05-01 09:16:15
  • #3
Sounds somewhat realistic. However, on the last page you forgot to remove the provider's name, so you can see who it is ;)
 

Legurit

2016-05-01 09:26:22
  • #4
I get a headache when I read this... can you please scan it properly once again? If you have it digitally, just upload it digitally... whether it is ELK or Horstwalter GmbH doesn’t matter to anyone anymore at this point (unless that should argue against uploading the PDF).

I have to admit that it wasn’t very clear to me what is included in the house price and what is in the additional costs (but that also depends on the format). The garage, for example – is it included in the additional costs? Overall, it feels like it could fit. But please be aware that, for example, with €1700 material in the sanitary sector (depending on the number of bathrooms) you are rather getting the standard – the same applies to the other items (flooring, tiles, etc.).
What actually happens with the €5,000 upgrade flat rate? Have you already upgraded the electrical?
 

nordanney

2016-05-01 12:04:51
  • #5
But you have already seen that the land purchase is included in the "additional costs," haven't you?
 

Similar topics
14.08.2012Build a home? Land in prospect19
25.03.2012Land now - house construction next year23
28.05.2013I am getting a plot of land as a gift. How do I finance the construction?16
03.01.2014How much land and house can we afford?25
20.07.2014Pay for the land in cash or finance it?14
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
12.12.2014Build a house? Financial advisor says the land and financing are okay15
16.02.2015Property purchased - Is financing/loan for house possible?13
05.04.2015Property reserved. Financing is pending52
16.06.2015Buy property now, and build in 3 to 5 years?52
15.06.2015Property and additional costs - is the construction sum realistic?16
21.04.2016Is financing with land and equity possible like this?20
15.05.2016Own home - Planning the property / Financing with income ok?22
18.05.2016Additional costs when purchasing a plot of land - property tax?55
13.08.2016Variable or fixed financing for land?11
08.08.2017Buy land with cash? How to build financing?44
01.02.2017Financing plan for new construction on existing property34
29.11.2017House and property €284,000 financeable?57
29.08.2019Loan amount in Berlin with existing land14
08.01.2023Finance the property, construction starting in 2 years. How to finance?17

Oben