Hello!
I want to keep the option open for the installation of a shower bath in the attic at some point.
The developer would prepare it for about €800:
-> Connections for cold, hot, and wastewater in the shaft up to the attic, closed as a ring line with threaded T-pieces, wastewater branch DN100 above the raw floor with end cap

Is the price fair, or could I just have a 100mm KG empty conduit installed (about €350)?
Or would the subsequent installation of additional (above-mentioned) pipes into this empty conduit plus connections etc. be too complicated and ultimately even more expensive?
How would you decide if money were very tight right now?

Thanks for your assessment!
 

wiltshire

2025-07-07 10:13:18
  • #2
The price is set so that it is worthwhile for you and that the developer makes a good profit.
 

wiltshire

2025-07-07 10:36:08
  • #3
I am not a good advisor when it comes to saving. Therefore, I did not answer this question.
 

kbt09

2025-07-07 13:14:15
  • #4
Let it be done, because with a 100mm KG pipe you are not at all well prepared as the only preparation. Because you need connections for toilet waste water, but also shower waste water as well as water supply lines. And everything should work later with the existing connections. The price difference from 350 to 800 should not be decisive here.
 

andimann

2025-07-07 15:18:37
  • #5
Hi,
so if he already wants 350 euros just for a KG empty conduit, I find 800 euros rather cheap. Definitely get it done!
But - check if you might run into problems with a very long ring circuit. (=Water takes forever to get warm at the tap) or branch connections (the water in the pipes really gets stagnant).
Best regards, Andreas
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
26.09.2011Finding tiles from other manufacturers / sample selection for builders13
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
16.07.2012The builder "outsources" fixed-price services to subcontractors12
03.08.2012Contract Supplement to the Construction Contract by the Developer36
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
18.02.2014Massive problems with the builder - is contract termination possible?33
23.06.2014Developer charges heavily for replanning - justified?12
08.10.2014How do you search for a suitable property developer?30
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
01.03.2015The developer does not build according to the plan14
13.06.2015New construction with developer / construction drawing documents23
10.09.2016Empty conduit from the supply room to the attic 50mm - sufficient14
11.04.2021Plan a conduit for Telekom?21
06.06.2020Pull the cable through the conduit20
01.09.2020Which conduit for LAN cable?32
08.12.2021Would you build yourself again or use a developer?31
07.05.2024How to seal a conduit with an underground cable?26

Oben