Screed wall correction decoupling

  • Erstellt am 2021-03-17 21:33:56

Keishadow

2021-03-17 21:33:56
  • #1
We just got the screed freshly installed and one wall was open at the bottom because of the underfloor heating. Now the opening turned out to be higher than it should be and the screed is now slightly behind the wall and the hole is still visible by about 2-3 cm. The contractor said I should fill it with PU foam and cut it straight. Then the floor would still be decoupled from the wall and once the baseboard is installed, the hole won’t be visible anymore. Chiseling away some of the screed is not an option because there is underfloor heating inside. Would that really be the best/quickest way to solve this here? PU foam in, cut off, done? Many thanks in advance for your tips :-)
 

KlaRa

2021-03-17 22:26:06
  • #2
Hello questioner. If I can see correctly in the photo, the screed was applied along the entire length of the wall with a setting strip against the wall. There was apparently a wall opening at one spot. Here the setting strip was "flapping" without any backing pressure in the air; through the screed mortar, the setting strip was pushed into the "wall niche" by smoothing and compacting, so that after hardening it now forms a curve projecting into the wall opening. The mistake was that the wall opening should have been protected with a longer hardboard strip so that the screed mortar could not be pressed into the niche. The fact that the wall plaster was also applied too high at this point worsens the whole situation somewhat in that this opening, or let’s call it "joint", would have to be covered in height by the later baseboard. PU foam must not be used in this case at all! The foam would develop uncontrollably in the wall opening, meaning it would fill the dead space somewhere there.

Solution: The screed layer should correct the edge line of the screed, meaning: shorten the belly-shaped extension with a shadow joint saw. If then the setting strip is put back "properly", so that it reaches up to the upper insulation layer, the visible joint/wall opening in the horizontal can be closed with wall plaster. Before that, it is essential to ensure there are no mortar lumps left in the edge joint. Otherwise, sound bridges are inevitable. Everything else is not proper and professional. Your wish for regulation-compliant execution in detail is not "nitpicking", it is therefore not pedantry, but justified! The screed layer cannot excuse himself, because he should have set this spot properly (shift-proof and pressure-resistant) before the screed mortar was installed. ----------------------------------- Regards: KlaRa
 

Similar topics
12.02.2013Heating single-family house, underfloor heating conversion, insulation, gas boiler defective19
06.03.2013Pump noises in underfloor heating, pump in living room, noise disturbance13
30.03.2015Underfloor heating in the bathroom sufficient or additional heating - wall heating?22
22.08.2014Underfloor heating or not?20
20.03.2015Tiles, vinyl, or other types of flooring with underfloor heating?23
14.08.2015Underfloor heating or radiators?12
20.10.2015Underfloor heating on the ground floor and upper floor, radiators in the basement?15
19.03.2016Underfloor heating vs. flat radiators14
15.04.2016Is the cost of underfloor heating completely exaggerated?44
08.06.2016Questions about underfloor heating - new subfloor/screed/granite tiles14
08.02.2017Underfloor heating connections in the wrong room13
15.03.2017Expert assessment for underfloor heating in a single-family house10
19.09.2017Electric connection floor heating10
12.11.2017Underfloor heating / Wall heating / Ceiling heating - Alternatives?18
25.11.2017Underfloor heating is not getting warm - 20,000 kWh consumption11
21.02.2018Too cold to install the underfloor heating?11
07.03.2018Digital thermostats for underfloor heating: useful? Is the extra cost justified?24
09.03.2018Radiator or underfloor heating: What is recommended under these circumstances?23

Oben