The Biny
2022-11-17 22:38:16
- #1
We started work at our construction site two weeks ago and the surveyors were there to carry out the rough staking out. Two days later the site manager was there and did a final inspection before the groundbreaking and excavation began the next day. Now, after the excavation is finished and L-shaped stones were actually supposed to be placed at the edge, it suddenly became apparent that the rough staking out had not been left as the surveyor had done, but had been moved 5 meters forward in total. By comparing pictures from the surveyor and the site manager, it was found that someone must have tampered with the stakes strategically during those two days and moved them forward. The excavation now has to be corrected and we have to expect additional costs. My questions for now would be, first of all, has anyone else experienced this problem? And who is legally responsible now? Or does the insurance even cover this at all? The police have been notified, and a report against unknown persons is in progress.