Hello everyone,
I learned today from my neighbor that we (as the client) are allowed to withhold 5% of the contract sum as security.
The contract states:
The client is entitled to demand the provision of a so-called completion security. If the contractor does not provide this security for the timely completion of the work without major defects in the amount of 5% of the contract sum in accordance with § 650 m paragraph 2 of the Building Code, the client is entitled to withhold interim payments up to the amount of the owed security.

QUESTION:
- Who has done this? What was your experience?
- Did you inquire with the general contractor or directly deduct at the first payment? Our first payment was only with 2%
- Until when may it be withheld? According to the Building Code, until the end of the warranty period
- Must the payment possibly be transferred to a blocked account?

Thanks for your answers
 

Vicky Pedia

2020-06-09 21:26:09
  • #2
Basically, you have a claim to a 5% retention, that is correct. However, the contractor can demand the payment upon submission of a warranty bond, i.e., a bank guarantees payment up to 5% in case of damage.
 

Andre77

2020-06-09 21:55:34
  • #3


you did receive a warranty bond from LVM...
 

immermehr

2020-06-09 22:47:18
  • #4


That means that if you build with Heinz von Heiden, you cannot withhold the 5%?
 

Andre77

2020-06-09 22:55:10
  • #5
Good question, in my opinion you would then have drawn twice, your retention and the warranty bond. Maybe others can say more about that.
 

HilfeHilfe

2020-06-10 07:11:38
  • #6
Either or. The good thing about the guarantee is that after full disbursement you also become the owner in the land register. Currently, everything would only need to be registered as a preliminary note.
 

Similar topics
19.02.2015Development costs §127 Building Code12
22.09.2015Building Code - Developer Contract - Postponement of Contractual Handover Date14
18.01.2016Payment of final installment and acceptance44
03.05.2016Please evaluate the payment plan25
08.08.2016Payment before or after completion of the construction phase?51
02.02.2018Financing strategy - increase income by payment of 3?18
15.10.2019Questions on the interpretation of § 34 Building Code59
14.04.2020Security deposit according to §650 of the Building Code20
06.05.2020Liberation § 31 Building Code: Roof pitch, roof shape, roof structures15
09.03.2021Withholding payment for defects in the shell construction74
10.04.2021Delays with the general contractor, no deadline set according to § 650 Building Code65
21.08.2021§34 Building Code: Building Window and Garage21
26.08.2021House purchase from uncle - Monthly payment or take a loan?33
29.12.2022Special right of termination according to § 489 Building Code - Refunds15
02.10.2022Retention after house acceptance - is substitute performance possible?11
09.11.2023Concrete light shaft corner broken in shell construction - retention justified?14
29.02.2024Payment plan - 5% retention not regulated11

Oben