Mueller9999
2016-06-30 22:22:32
- #1
Hello,
I have received the following offer from my basement builder:
"With the 25cm thick floor slab with a double layer of reinforcement using Q 424 mats, the following costs would occur.
Approximately 20 reinforcement mats are needed in the basement floor slab, the weight difference between a Q188 mat and a Q424 mat is approximately 42.7 kg per mat, so we come to an additional steel content of a total of 854 kg.
More steel in the floor slab = 854 kg * €2.00/kg = €1708.00 Additional concrete (increase from 20cm to 25cm) = 88.95 m² * 0.05m = 4.45 m³ * €188/m³ = €836.60
That makes a total of €2544.60 for the desired execution of the basement floor slab"
Unfortunately, I have no knowledge in this area at all. Is this a good offer? Or should I take the 20 cm floor slab without extra charge?
->>> under the floor slab is slate :-(
I have received the following offer from my basement builder:
"With the 25cm thick floor slab with a double layer of reinforcement using Q 424 mats, the following costs would occur.
Approximately 20 reinforcement mats are needed in the basement floor slab, the weight difference between a Q188 mat and a Q424 mat is approximately 42.7 kg per mat, so we come to an additional steel content of a total of 854 kg.
More steel in the floor slab = 854 kg * €2.00/kg = €1708.00 Additional concrete (increase from 20cm to 25cm) = 88.95 m² * 0.05m = 4.45 m³ * €188/m³ = €836.60
That makes a total of €2544.60 for the desired execution of the basement floor slab"
Unfortunately, I have no knowledge in this area at all. Is this a good offer? Or should I take the 20 cm floor slab without extra charge?
->>> under the floor slab is slate :-(