Received an offer from a builder: Cost of shell construction - experiences?

  • Erstellt am 2015-02-20 22:25:32

Diddy

2015-02-20 22:25:32
  • #1
Good evening everyone,

things are slowly entering the crucial planning phase with us as well.
Today we received an offer from our builder.
Interior walls can be arranged differently as desired.
Now I wanted to hear your opinion on whether this is within an acceptable range for what is offered...
For now, it is only about the shell construction. Too much is still unclear regarding the rest...

Thanks in advance for your answers/experiences
 

Koempy

2015-02-21 09:50:35
  • #2
You can't say that without a comparable offer but 2 pages for the entire shell construction seems very little to me. And a few details are described so generally that a layperson probably reads something different than what they actually get
 

EveundGerd

2015-02-21 10:35:41
  • #3
Is there a detailed construction service description for this?

Are you building according to the Energy Saving Ordinance or are you still installing an ETICS?

Are there comparative offers?
 

Diddy

2015-02-21 10:53:16
  • #4
: That is always the big problem. The layperson thinks everything is included and everything is great. And ends up disappointed...
: There is also a specification. However, this mostly includes the following trades. A Kfw70 is to be built, which should be suitable as is.

The offer comes from a regional construction company that has built many houses in our new development area and the surroundings. So far, we have not heard that anyone was dissatisfied. At least by and large...
There is also no other offer because we have committed ourselves to this company...
 

Sebastian79

2015-02-21 12:59:27
  • #5
Yes, then why are you still asking?
 

Diddy

2015-02-21 14:52:37
  • #6
Because I am interested in whether the price is reasonable or miles away from the usual prices. Is there room for negotiation, or not at all. You don’t have to argue about 1000€, but about 10000 you should... That’s what it’s about for me. And also how you assess the quality of the materials and the technical execution.
 

Similar topics
14.11.2011Shell construction still this year15
05.09.2015Cracks in masonry (shell construction)14
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
24.04.2015Buy tiles during shell construction24
27.02.2015Purchase shell construction and complete it including financing15
11.02.2016Cost per cubic meter of built-up shell space14
07.05.2016Buying a shell construction - Experiences21
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
20.04.2017Payment plan with 35% after the shell construction, okay?10
05.05.2017Rough construction flat-rate offer - forgotten necessary items11
06.09.2017Add a wind catch later to the shell construction17
07.10.2017From when must the shell construction be dry or sealed?16
18.12.2017Offers for single-family house shell construction and basement received - your assessment?21
31.01.2022Possible savings in self-performed structural work37
27.08.2018New building shell construction selection: Choose a company or architects?52
18.09.2018No offer for electrical work - must the shell construction be stopped?12
09.10.2018Costs for shell construction and roof covering/insulation - fixed price offer okay?25
02.02.2021The contractor wants to issue an invoice for planning services60
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17