VelBau
2016-08-21 13:53:23
- #1
Good day everyone,
I have received the contract for work from our potential BU with the following payment schedule:
(Einfamilienhaus, 10.7 m x 12.7 m / 25° SD/Drempel: 1.375 m / with basement/bay window,
move-in ready, KFW 55 with ground source heat pump and garage 9x3m)
1. Submission of the building application 5.0 %
2. After completion of the foundation slab 10.0 %
3. After completion of the basement ceiling 10.0 %
4. After completion of the ground floor ceiling 10.0 %
5. After completion of the carpentry work 10.0 %
6. After completion of the roof covering 10.0 %
7. After installation of the windows 7.5 %
8. After screed work 10.0 %
9. After completion of the exterior facade 7.5 %
10. Upon completion and preliminary acceptance 15.0 %
11. After final acceptance before moving in and handover 5.0 %
What do you think, is this plan acceptable?
Thank you
I have received the contract for work from our potential BU with the following payment schedule:
(Einfamilienhaus, 10.7 m x 12.7 m / 25° SD/Drempel: 1.375 m / with basement/bay window,
move-in ready, KFW 55 with ground source heat pump and garage 9x3m)
1. Submission of the building application 5.0 %
2. After completion of the foundation slab 10.0 %
3. After completion of the basement ceiling 10.0 %
4. After completion of the ground floor ceiling 10.0 %
5. After completion of the carpentry work 10.0 %
6. After completion of the roof covering 10.0 %
7. After installation of the windows 7.5 %
8. After screed work 10.0 %
9. After completion of the exterior facade 7.5 %
10. Upon completion and preliminary acceptance 15.0 %
11. After final acceptance before moving in and handover 5.0 %
What do you think, is this plan acceptable?
Thank you