Payment of the final installment after assurance of defect rectification

  • Erstellt am 2017-02-15 06:57:49

Timberwood

2017-02-15 21:23:06
  • #1
The final installment amounts to 7,500 euros, I will call the expert directly tomorrow and ask about it.

It was not agreed upon, but it will be added to my list of things to consider for the next house construction ;)
 

ypg

2017-02-15 21:46:01
  • #2
What kind of contract is it anyway? According to the Building Code or according to the VOB? "Due after acceptance of the construction" sounds to me like the Building Code, where no retention is regulated, see "due after acceptance of the construction"... that is a regulation and not a saying!

Best regards, Yvonne
 

Knallkörper

2017-02-16 20:33:44
  • #3
Even with the agreement "due after acceptance," the client is entitled to raise the objection of defect, so that the contractor usually cannot enforce his claim. This also applies to fixed agreed payments according to the payment schedule.
 

Otus11

2017-02-16 22:53:12
  • #4
641 para. 3 Baugesetzbuch provides the answer.
 

Bieber0815

2017-02-17 07:27:06
  • #5
That was already largely clear, the recent posts were about a guarantee security.
 

Similar topics
19.02.2015Development costs §127 Building Code12
22.09.2015Building Code - Developer Contract - Postponement of Contractual Handover Date14
17.01.2017Question about building inspection10
02.09.2019Install securing against rolling on the sleeping floor for building acceptance12
15.10.2019Questions on the interpretation of § 34 Building Code59
14.04.2020Security deposit according to §650 of the Building Code20
06.05.2020Liberation § 31 Building Code: Roof pitch, roof shape, roof structures15
10.04.2021Delays with the general contractor, no deadline set according to § 650 Building Code65
21.08.2021§34 Building Code: Building Window and Garage21
29.12.2022Special right of termination according to § 489 Building Code - Refunds15