Order screed - plaster

  • Erstellt am 2016-04-27 15:18:27

Christian123

2016-04-27 15:18:27
  • #1
Hello everyone,

normally the sequence is first the interior plaster, then the screed. Since in our case (Poroton brick walls) the floor slab is insulated from the inside with 16cm PUR, I would like to change the sequence... so specifically from the floor slab: vapor barrier, 10cm PUR (continuous), laying empty conduits for electrical, ventilation and plumbing, fitting the remaining 6cm PUR with subsequent pearl granulate around the pipes, Rolljet, underfloor heating, screed, then only pulling the plaster up to the screed (as sound insulation I would place a dam strip underneath). Now you keep reading that the plaster has to be pulled up to the floor slab for airtightness... is that really the case? Can this be solved otherwise?

Regards,
Christian
 

nordanney

2016-04-27 15:23:19
  • #2
Internal insulation is not unusual. Still, first plaster and then the rest. You also do not want to have all the dirt on the screed.
 

KlaRa

2016-04-27 15:42:30
  • #3
Hello Christian. The "usual way" in residential construction is indeed first wall plaster and then the screed. But of course it can also be done differently! The only important thing is that wall surfaces and screed do not form a rigid connection (because of sound insulation). The plasterer must then ensure a decoupling between the (to be plastered) wall surface and the screed surface. He will then provide a distance strip under the lower edge of the plaster. Higher costs will occur when grinding the screed, before the floor covering work. Because the mortar blobs caused by plastering work on the screed, unavoidable, must be removed again. The plasterer can do this at his own expense (if he does not want to cover the screed surface), or the floor layer as a paid main service. But this then has nothing to do with a "cleaning grind" (ancillary service of the floor layer)! ------------------ Best regards: KlaRa
 

xray107

2016-04-27 15:46:21
  • #4
What advantages do you see in the sequence screed/plaster compared to plaster/screed. We also insulated on the BP and had the sequence plaster/screed...
 

nordanney

2016-04-27 15:51:52
  • #5
None.
 

bortel

2016-04-27 15:54:48
  • #6
You can make the baseboards flush and this is quite easy because you can place something directly on the [Estrich]. Doing it the other way around is always more difficult because the [Estrich] will never be 100% exactly the same height...
 

Similar topics
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
10.05.2015Screed uneven - defect removal refused52
13.04.2017Screed with gold sand17
07.08.2016Upper floor without screed - only concrete floor15
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
31.10.2016Heating the screed with the utility provider?!12
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
05.04.2017Super disaster - water pipe burst, screed damp31
30.04.2017Screed applied too high - room height consequently lower11
05.08.2017Screed necessary? Unfinished but insulated attic23
19.08.2017Technical room before installing screed: should the technology be painted now or later?16
05.11.2017Screed in the bathroom applied incorrectly - What to do?18
06.10.2019Base plate with concrete core activation. What is your opinion?46
27.12.2017Underfloor heating heating demand with at least 60 mm screed30
24.01.2018Is the floor still too wet or is it already normal?27
02.08.2018SchwörerHaus: Seam in the plaster between two floors? Is that so?27
03.02.2019Underfloor heating in the floor slab - advantages and disadvantages?15
12.10.2020Q2 Plaster cracks / minor defects - is this a defect or tolerable?17

Oben