Network connection or construction power, which comes first? Experiences?

  • Erstellt am 2018-05-03 17:47:04

MangoLychee

2018-05-03 17:47:04
  • #1
Hello dear ones,

we are building a turnkey solid house stone by stone. We have, however, contracted the electrical work ourselves. Our construction manager has now given us the documents for a grid connection. He said to submit them immediately.

The shell construction company is applying for the construction power.

However, our electrician now said that he wants to apply for the grid connection only after the foundation slab has been laid. He doesn't think it makes sense before that.

Now we are a bit puzzled. Who is right? Do we really have to apply for the grid connection so urgently now, or can it wait? Does it have any consequences if the shell builder applies for the construction power and we have not yet submitted the grid connection application?
 

Mycraft

2018-05-03 19:02:10
  • #2
Actually, you have to apply for all media as quickly as possible. It can then sometimes take months until everything has finally arrived and is also located/connected in the house.

My power column was in place even before the excavator came for the foundation, and that was a good thing.
 

Similar topics
06.12.2017Until when must construction power be taken?22
23.06.2015Secondary construction costs, amount of construction electricity/construction water, how much?18
29.04.2016Organize construction electricity/construction water yourself?31
19.10.2017Temporary power supply - What costs are involved?19
05.07.2018Temporary electricity stolen - amount of compensation?17
20.07.2018Construction power or house connection? How much construction power is needed?12
19.03.2019Construction power is being connected. Does the builder have to be present?10
20.05.2019Temporary power also through alternative suppliers?10
04.10.2019Easily switch temporary power provider?21
11.05.2020Construction power help, who can give tips?17
28.06.2020Connection for network power supply very expensive?!23
10.01.2022Determine construction power costs / eOn charges too much36
23.10.2023Judgment on construction power supply - assessments / experiences?10
09.10.2024Construction electricity/construction water costs are the responsibility of the builder11

Oben