aytex
2014-03-09 11:52:52
- #1
Hello forum
Attached is our drainage plan.
About 42m need to be "excavated"
About 25m of main pipe for wastewater need to be laid
About 41m of main pipe for rainwater need to be laid.
I have now received a fixed price. The company charges 900€ for these works including tightness testing.
I wanted to roughly calculate that:
In total I need about 66m of KG main pipe with DB 125. The meter costs approximately, let's say, 4.50€
That comes to about 300€. Plus seals, branches, and bends, let's estimate it at 350€.
So there remain 550€ for the excavation, laying, and backfilling. What do you think, is that reasonable? Let me put it this way, if it should be possible to do this work in one day, meaning start at 7:00 a.m. and finish at 5:00 p.m., I find an hourly wage of 55€/h already somewhat high, or am I on the wrong track?
Regards
Attached is our drainage plan.
About 42m need to be "excavated"
About 25m of main pipe for wastewater need to be laid
About 41m of main pipe for rainwater need to be laid.
I have now received a fixed price. The company charges 900€ for these works including tightness testing.
I wanted to roughly calculate that:
In total I need about 66m of KG main pipe with DB 125. The meter costs approximately, let's say, 4.50€
That comes to about 300€. Plus seals, branches, and bends, let's estimate it at 350€.
So there remain 550€ for the excavation, laying, and backfilling. What do you think, is that reasonable? Let me put it this way, if it should be possible to do this work in one day, meaning start at 7:00 a.m. and finish at 5:00 p.m., I find an hourly wage of 55€/h already somewhat high, or am I on the wrong track?
Regards