Interior plaster / Exterior plaster drying

  • Erstellt am 2012-10-26 13:30:44

Hilaria

2012-10-26 13:30:44
  • #1
Hello, I have a few questions again: after actively working 4 days on our construction site over the last 5 weeks (window installation and electrical conduit installation), we are a "bit" behind our planned construction schedule. By then, the rough installation of plumbing and heating as well as the interior plaster should already be completed. Next week are the autumn holidays here and the construction site will be idle then as well. Earliest active day: 5.11.

Today the site manager told me during a meeting on the construction site that he plans to complete the interior plaster, screed, heating system, and exterior plaster still this year.

According to our construction schedule, the exterior plaster should only be done quite late (March).

Now my question is: what would be the better option regarding the drying of the building? Exterior plaster still this year or preferably next year? The site manager says he wants to protect against moisture in the winter.

As far as I could read, exterior plaster should not be applied below 5 degrees (even at night). Nobody can guarantee that anymore, right?

Thanks Hilaria
 

vokono

2012-10-26 21:05:26
  • #2
Hello,
in your situation, I would also prefer to wait until next year, at least with the exterior plaster (if possible). First, better to "live dry" in the hut a bit. Provided that is possible over the winter. For the interior plaster, I would organize dehumidifiers if possible. Aside from that, there is a frost protection additive for interior plasters. It may have the disadvantage that the plaster does not suffer frost damage but takes longer to dry.
 

Hilaria

2012-10-27 14:46:23
  • #3
Hello,
we actually do not want to set up dryers but rather, as K.Bodbeck wrote, to keep the house as dry as possible over the winter.

Our site manager says it "doesn't" matter, on the contrary, once the exterior plaster is applied, it protects against moisture in winter. Well, I am not sure if that is true.

Scaffolding costs affect us only a little, we have a fixed price. But we believe that this really plays a minor role here. On our construction site, the crane and scaffolding stood for almost 4 months!!! partly unused for weeks, last week the scaffolding was dismantled only to be reassembled in about 3 weeks, strange, strange.

The heating must still run before the winter break, otherwise there will really be trouble....

Well, the exterior plaster is the only thing that unsettles me.

Best regards
Hilaria
 

Bauexperte

2012-10-27 15:44:32
  • #4
Hello,


Basically, +5° is required; whether day or night.

Ask your site manager if he wants to cover the scaffolding? That can bring a degree or two ...

Kind regards
 

Similar topics
02.02.2009Building materials are stolen at the construction site12
01.04.2020Construction Manager Area Neukirchen-Vluyn (Duisburg/Kleve/Wesel)10
10.02.2014Commitments from the construction manager - Trust relationship13
09.03.2014Construction manager missing10
09.10.2014What when in house construction?17
22.04.2015Window, roller shutter, exterior plaster10
17.11.2016Are venetian blinds legally considered part of the exterior plaster?11
09.01.2017Interior and exterior plaster in winter10
09.11.2019Sound problem: Does noise come through masonry - through the exterior plaster?20
09.08.2017Is exterior plastering possible before interior plastering in summer?10
13.11.2017Construction scheduling - Who has to create it? General contractor, site manager?11
11.10.2018Waste on the construction site - What is tolerable?138
10.03.2019Garage 8m x 7.5m gable roof, strip foundation, exterior plaster costs10
31.05.2019The construction manager does not come, does not check, or he doesn't care about anything16
23.03.2020Curfew: Am I still allowed to go to the construction site in Bavaria?73
09.04.2020Visit the construction site for ventilation?17
15.12.2020Has the professional association blocked the scaffold during self-performance?23
21.01.2021Exterior plaster is uneven, window sills are too short, tightness of the ETICS (External Thermal Insulation Composite System)63
19.08.2021House building - an eternal construction site?33
21.09.2022Camera / mobile phone for documentation in the workshop or construction site13

Oben