Good morning,
We have a problem, our shell construction is completed up to the mezzanine floor. Unfortunately, the bricks we selected were not delivered to us and now they have to be replaced. This naturally involves a new delivery time.
My question is, can the construction continue without the bricks? I mean further structural work, windows, interior work, etc.?
Best regards