posterino
2012-06-16 11:47:40
- #1
Hello dear forum,
we are currently having our single-family house built by a developer.
Three days ago, I inspected the construction site and was horrified to find that drying devices have been set up throughout the entire ground floor and in all rooms the screed has been drilled (one to two openings per room) and hoses have been laid in for drying.
On all walls (gypsum plaster), from the floor upwards, I found water stains about 15-20 cm high.
Our house has no basement and is built on a slab.
The floor construction is as follows:
slab, waterproofing membrane, insulation (PS rigid foam WLG 035), cement screed - including underfloor heating.
No floor covering has been installed yet.
Our site manager has not informed us of this serious defect until today.
After requesting a statement by email yesterday, I have still received no response.
Our house handover (end of June) and thus the move-in date are therefore obsolete.
My huge request now is: how should I proceed or what should I consider to avoid unpleasant surprises later regarding mold and other consequential damage.
Questions:
Should I stop all payments to the developer immediately (outstanding claims approx. 22,000 euros)?
Can I charge the developer for the electricity (approx. 100 kilowatt-hours/day) for the drying devices - meter readings have been recorded?
We have already terminated our rental apartment and must now try to negotiate an extension with the landlord. If repairing the construction defects takes a very long time, e.g. due to dismantling because otherwise the moisture cannot be removed from the floor, specifically the moisture under the insulation, can I claim the additional rental costs from the developer? The building contract only states that in case of delay 50 euros per day are paid from Monday to Friday and the maximum claim is 5% of the construction sum. Does this also apply to delays caused by legal disputes?
And simply any tips on how we should proceed in this case. We have a small daughter of 13 months and definitely want to avoid any risk that she might have problems due to mold or other construction defects.
Many thanks to all who can give us helpful advice.
Bernd
we are currently having our single-family house built by a developer.
Three days ago, I inspected the construction site and was horrified to find that drying devices have been set up throughout the entire ground floor and in all rooms the screed has been drilled (one to two openings per room) and hoses have been laid in for drying.
On all walls (gypsum plaster), from the floor upwards, I found water stains about 15-20 cm high.
Our house has no basement and is built on a slab.
The floor construction is as follows:
slab, waterproofing membrane, insulation (PS rigid foam WLG 035), cement screed - including underfloor heating.
No floor covering has been installed yet.
Our site manager has not informed us of this serious defect until today.
After requesting a statement by email yesterday, I have still received no response.
Our house handover (end of June) and thus the move-in date are therefore obsolete.
My huge request now is: how should I proceed or what should I consider to avoid unpleasant surprises later regarding mold and other consequential damage.
Questions:
Should I stop all payments to the developer immediately (outstanding claims approx. 22,000 euros)?
Can I charge the developer for the electricity (approx. 100 kilowatt-hours/day) for the drying devices - meter readings have been recorded?
We have already terminated our rental apartment and must now try to negotiate an extension with the landlord. If repairing the construction defects takes a very long time, e.g. due to dismantling because otherwise the moisture cannot be removed from the floor, specifically the moisture under the insulation, can I claim the additional rental costs from the developer? The building contract only states that in case of delay 50 euros per day are paid from Monday to Friday and the maximum claim is 5% of the construction sum. Does this also apply to delays caused by legal disputes?
And simply any tips on how we should proceed in this case. We have a small daughter of 13 months and definitely want to avoid any risk that she might have problems due to mold or other construction defects.
Many thanks to all who can give us helpful advice.
Bernd