How long until the building application?

  • Erstellt am 2013-07-02 14:48:00

mcburns

2013-07-02 14:48:00
  • #1
Hello dear forum!

We signed the house contract in mid-May and at that time it was said that the shell construction would definitely be finished by winter.

So far, there have repeatedly been some uncertainties that made it impossible for the construction company to send out the building application.

But now we are waiting for the approval so that we can finally go there and sign.

How long did it take for your construction company to send out the building application?

Is it normal that the interest-free provision period has already expired before the house is finished?

Assuming the building application would be sent out in the next few days and approved in October (=3 months), would it still be possible to at least finish the shell construction for a bungalow this year?
Can construction then start immediately (assuming it is still frost-free)
or do I have to factor in some other points?

I would be happy to receive answers

Best regards
 

Musketier

2013-07-02 16:28:12
  • #2
I can't say exactly how long it took to submit the building application, as several things were pending with us. The building application has now been approved for 3-4 weeks.

Our contract states that once the financing commitment is in place, the sample selection has been completed blablabla, and the detailed planning has been signed off, the company has 4 weeks until construction starts. So far, we have fulfilled all our tasks except for the sign-off. The only problem is that the detailed plans are delayed, and we cannot sign them off. So the 4-week period does not start running.

Now it is vacation time, and after that our detailed plans will be processed. Construction start is therefore earliest at the end of August.
 

ypg

2013-07-02 19:49:04
  • #3
You can take a look at my construction blog, which is linked here. We also had the "problem" that we miscalculated and didn't consider things that take time. Our waiting is listed there in detail. We're simply not the only ones who are building ;)
 

chrizzt

2013-07-03 21:15:03
  • #4
we have finished the shell construction and are already past the rent-free period. due to the long winter, everything has been delayed by 3 months.
 

Naddl

2013-07-04 11:53:28
  • #5
They have already started building with us and we are still waiting for the [Notarvertrag] :-) The city is taking an enormous amount of time to set up the land registers... The building permit was also available within 4 weeks.
 

DerBjoern

2013-07-04 13:30:16
  • #6
After the contract was signed, the building application was sent out after approximately 3 weeks.
 

Similar topics
14.11.2011Shell construction still this year15
02.01.2012Semi-detached house - who submits the building application first, wins?29
29.10.2013Property reserved, construction financing plan, architect/building permit application21
17.12.2014Building application "deferred". What does that mean?19
28.02.2015Building application submitted/open detailed questions/looking forward to suggestions39
15.06.2015Garage - Building Application - Confusion36
30.10.2015Can the building application be submitted this year?14
01.02.2017Building application is becoming increasingly complicated!20
27.04.2017Carport deviation from the building application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
06.09.2017Add a wind catch later to the shell construction17
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?44
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
08.08.2018Neighbor objects after approved building application69
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
17.12.2018What is set in stone in the building permit application?10
21.10.2019Construction start still this year (November)?14
01.12.2020Shell construction with an expired building permit43

Oben