Fay1983
2019-09-11 17:53:33
- #1
Hello,
in another thread I have already described one or the other problem with our developer. I hope I am posting in the right place here, as we are now facing an "official" question. We are building turnkey with a developer and acquire the land including the house after handover in February 2020. The house is currently being "closed up," meaning the shell is complete, the roof is on, and the windows are installed.
The land slopes slightly (!) downwards towards the rear property boundary; however, at the start of construction, the land was heavily filled, so that the foundation slab is now relatively high above the original terrain line. The developer does not provide for securing the loose soil, as this is considered part of the "external facilities." At that time, I did not think much of it, since the developer should know what he is doing. Several garden landscapers have now inspected the property, as we wanted to know what costs (which were not planned) we should expect. It would need to be secured to a height of about 1.70m and additionally filled to achieve a level surface at the height of the foundation slab, overall including tree removal (these are now half buried) and fence installation about 10,000 euros. To legally protect ourselves, I then called the responsible building authority to inquire about possible requirements (yes, in our case permits are required from 2.00m). By chance, I spoke with exactly the officer handling our building application, we had a conversation and—long story short—it turned out that the developer applied for the construction incorrectly! The submitted documents do not match the current actual condition. The building authority feels "deceived" and will summon the developer for a hearing; furthermore, there will now be requirements imposed on the developer to secure the property.
My question now is: Do we actually have to bear the costs for the securing ourselves anyway? Exactly the same plans that we signed in the notarized contract were submitted for the building application. A construction plan with the (obviously only subsequently measured) actual terrain slope was only available to us after the notarized contract and building permit at the start of construction. We actually see the obligation with the developer, as he handed over the faulty plans both to the building authority and to us as buyers.
Has anyone maybe had a similar case?
Thanks and best regards
in another thread I have already described one or the other problem with our developer. I hope I am posting in the right place here, as we are now facing an "official" question. We are building turnkey with a developer and acquire the land including the house after handover in February 2020. The house is currently being "closed up," meaning the shell is complete, the roof is on, and the windows are installed.
The land slopes slightly (!) downwards towards the rear property boundary; however, at the start of construction, the land was heavily filled, so that the foundation slab is now relatively high above the original terrain line. The developer does not provide for securing the loose soil, as this is considered part of the "external facilities." At that time, I did not think much of it, since the developer should know what he is doing. Several garden landscapers have now inspected the property, as we wanted to know what costs (which were not planned) we should expect. It would need to be secured to a height of about 1.70m and additionally filled to achieve a level surface at the height of the foundation slab, overall including tree removal (these are now half buried) and fence installation about 10,000 euros. To legally protect ourselves, I then called the responsible building authority to inquire about possible requirements (yes, in our case permits are required from 2.00m). By chance, I spoke with exactly the officer handling our building application, we had a conversation and—long story short—it turned out that the developer applied for the construction incorrectly! The submitted documents do not match the current actual condition. The building authority feels "deceived" and will summon the developer for a hearing; furthermore, there will now be requirements imposed on the developer to secure the property.
My question now is: Do we actually have to bear the costs for the securing ourselves anyway? Exactly the same plans that we signed in the notarized contract were submitted for the building application. A construction plan with the (obviously only subsequently measured) actual terrain slope was only available to us after the notarized contract and building permit at the start of construction. We actually see the obligation with the developer, as he handed over the faulty plans both to the building authority and to us as buyers.
Has anyone maybe had a similar case?
Thanks and best regards