House connections and preparatory construction measures - what order?

  • Erstellt am 2024-01-08 17:04:02

Nida35a

2024-01-09 09:49:05
  • #1
For electricity, there was/is a connection box on the property, where the cable (for us 5x50qmm) was laid in the trench and connected to the construction power box at the future house. There was a water tap at the old house, that was the construction water.
 