Bauenaberwie
2022-11-15 10:53:18
- #1
Hello everyone,
we are now in the interior construction phase, meaning the remaining openings are to be closed. Afterwards, the screed is scheduled to be installed at the beginning of December. The interior plaster has now completely dried after 12 weeks. It is getting colder and inside the house it is still 1-2 degrees cooler than outside because the vapor barrier and insulation on the upper floor are not completely sealed yet. According to the site manager, it makes no sense to set up a small heater, but the construction power is supplied by the general contractor :D. Therefore the question is, does it make sense to heat a little with a 2KW heater? Many thanks
we are now in the interior construction phase, meaning the remaining openings are to be closed. Afterwards, the screed is scheduled to be installed at the beginning of December. The interior plaster has now completely dried after 12 weeks. It is getting colder and inside the house it is still 1-2 degrees cooler than outside because the vapor barrier and insulation on the upper floor are not completely sealed yet. According to the site manager, it makes no sense to set up a small heater, but the construction power is supplied by the general contractor :D. Therefore the question is, does it make sense to heat a little with a 2KW heater? Many thanks