And on Monday the masonry work will begin. How long do you think it will take? Two-story city villa Nothing special, except for painting and flooring, everything will be done by the company. Thanks in advance for your answers. We hope there will be no frost
We started building at the same time last year with the same parameters you mentioned. Except for painting and flooring, the general contractor did everything. Completion was planned for the end of April 2022, which was the case except for minor details. Our general contractor ordered everything immediately after the construction meeting, which was in January 2021, so that all the required materials were already available at the building materials dealer during the construction period. It may also depend on the region where the building is taking place. Our site manager told me in May that the only delays they had were with the heat pumps. I currently know 3 couples/families who are also building with our general contractor, and they are all progressing according to plan.