Geo-textile fleece at foundation - wrong robustness class (GRK)

  • Erstellt am 2024-07-27 02:19:27

Steve55

2024-07-27 02:19:27
  • #1
Hello everyone,

I have another question.

My earthworks contractor used GRK 2 fleece as a separating layer for the foundation, which I noticed afterwards.

However, the soil report states at least GRK 3. Is that a problem? Or should I just add another layer of GRK 3 fleece?

Currently, there is a layer of gravel above the fleece. But there will be at least another 1.5m of gravel on top.

Thank you very much in advance!
 