ypg
2021-10-27 00:44:06
- #1
Building staking 700
Soil survey 540
Certified site plan 700
House connection water/electricity up to the house + wastewater from the street 8,300
Energy consultant 5,000
One-time payment water supply and disposal 3,201
You strike that and replace it with 30,000-40,000€ additional construction costs.
A lot is missing. Soil surveys can cost rather double to triple, surveying costs run between 3,000-4,000, rainwater connection, permits, etc.…