Fast-setting screed on wooden beam ceiling, experiences?

  • Erstellt am 2024-03-19 16:20:57

Pound

2024-03-19 16:20:57
  • #1
Hello guys,

I am once again working on a small renovation at the house.. the kitchen is currently being renewed.

For the following two reasons, I ripped out the floor
- because the old heating pipes (unfortunately a single loop system) were already 50 years old
- and the rest of the floor structure (height) of the apartment had already been renovated, so I had a 3 cm step to the kitchen.

Previously, a "normal" screed was laid on foil and thin Styrodur boards, but it was already severely cracked, which I want to prevent as much as possible this time.

Originally, it was planned to apply a cast asphalt, but now it would cost a hefty 2600€ for 12 sqm (213€/sqm).. which is too expensive for me.

For time reasons, I would like to apply a fast screed by the company Baumit (allegedly usable after 3 days).

My questions to the experts here..

- how to best design the structure? Insulation - foil - Lewis boards - screed - impact sound insulation - parquet (16mm)
- how do I best protect the copper pipes from contact corrosion? I was thinking of such fiberglass pipe insulation see picture
- how thick should I make the insulation, I don't want to burden the joists with too much weight..

Thanks in advance
 

KlaRa

2024-03-21 09:56:04
  • #2
Hello questioner.
From the (informative) middle photo, it can be seen that the old screed construction had a buildup height of around 10cm.
If the not yet insulated/encased copper pipe is provided with appropriate protection, that is, an encasement, then 10cm - 6cm = 4cm buildup height remains.
That is practically "quite little".
I suggest compensating the entire area (after encasing the exposed copper pipes) with a lightweight screed, Thermocell or similar, up to the top edge of the encasement.
On this, a load distribution board made of HDF or MDF, impact sound insulation 20mm, PE foil, and on top of that a prefabricated screed made of gypsum fiberboard or as an OSB board.
This should then meet all requirements.
-----------------
Regards and good luck: KlaRa
 

Similar topics
14.01.2013Insulation / Vapor Barrier Top Floor Ceiling / Collar Beam, Open Ceiling14
26.04.2016Question about kitchen drainage / piping16
27.05.2016Plastic fittings/water pipes and insulating underfloor heating beneath screed?40
12.09.2016Water connection outside from the kitchen - possible?39
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
05.04.2017Super disaster - water pipe burst, screed damp31
26.02.2018Insulation under reinforced concrete floor slab KFW5520
27.07.2018Is it possible to measure the kitchen in the shell construction after the interior plaster is completed?10
22.07.2019Drain pipe not under the screed37
19.05.2021Substructure facade rhombus battens without insulation19
02.06.2023Marten in the roof insulation, what can I do???27
06.03.2021Mold problem in new kitchen - how to prevent it in the future?76
09.03.2021Reinforce floor slab insulation, reduce heat entry into the upper floor13
22.11.2023Very low construction height with underfloor heating in old buildings11
25.11.2022Mill underfloor heating or apply new screed?17
24.03.2023Work on basement ceiling insulation with stone wool48
28.07.2023Screed has been in for three days and is still wet?52
19.12.2024Laying parquet - Expansion joint in screed of varying height11
09.01.2025Vinyl flooring in the kitchen / Beam ceiling sagged / Should I lay it on tiles?11

Oben