Exclusion of warranty for exterior plaster

  • Erstellt am 2015-10-26 06:53:19

DaMutz

2015-10-26 06:53:19
  • #1
Good morning,

we are currently in the process of building our single-family house and are in the final stages of the expansion.

We now have the following question: under what circumstances can we terminate the contract with the company that is doing the exterior plaster? This company wants us to release them from the warranty because a few days after applying the base coat, the screed will be poured (there are supposed to be discolorations and chipping on the exterior plaster due to the increased moisture diffusion).

Since this demand was not/ is not part of the contract, we see this as a breach of contract on the part of the company. An alternative company is already ready to carry out the remaining work at short notice. We therefore want to get the current company out of the contract as soon as possible, as there are also considerable defects in the execution.

We are currently having this case reviewed by our lawyer. However, I would still like to get several opinions/experiences. According to our lawyer's initial statement, this is definitely a reason to terminate the contract. For a final statement, however, he wants to research other precedent cases in advance...

Has anyone experienced something like this or can give us advice?

Regards

DaMutz
 

nordanney

2015-10-26 08:29:25
  • #2
Well, I can understand the company's demand! If you have work done that can cause damage to the exterior plaster, I would, as a company, a) do the work at your own risk or b) have myself released from liability for this case (but only this one - all other warranty issues must of course remain unaffected). Why should the company cover the costs for color changes caused by you? If you are already talking to a lawyer, there must have been several problems already and you are very dissatisfied. Normally, I advise talking to people – but for you, it seems that it is already too late, right?
 

Bieber0815

2015-10-26 20:18:12
  • #3
Because screed is being applied inside, the plaster on the outside is supposed to flake? The same plaster that is supposed to hold up for many years all year round later? Can anyone explain this?
 

alexm86

2015-10-27 07:25:58
  • #4
With us, the plasterer's statement was: first the interior plaster and then after about 8 days the exterior plaster including [WDVS], because supposedly, the moisture from the interior plaster would escape to the outside and in doing so could "push away" the [WDVS] including the exterior plaster; he did not say anything about the screed.
 

Similar topics
29.09.2011Is construction pre-planning without signature / contract legally valid?12
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
22.04.2015Window, roller shutter, exterior plaster10
10.05.2015Screed uneven - defect removal refused52
13.04.2017Screed with gold sand17
28.04.2016Order screed - plaster14
04.07.2016Building without a contract - Concerns?39
07.08.2016Upper floor without screed - only concrete floor15
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
31.10.2016Heating the screed with the utility provider?!12
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
09.01.2017Interior and exterior plaster in winter10
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
09.11.2019Sound problem: Does noise come through masonry - through the exterior plaster?20
11.02.2017Heating of screed ready for covering23
05.04.2017Super disaster - water pipe burst, screed damp31
09.08.2017Is exterior plastering possible before interior plastering in summer?10
10.03.2019Garage 8m x 7.5m gable roof, strip foundation, exterior plaster costs10
21.01.2021Exterior plaster is uneven, window sills are too short, tightness of the ETICS (External Thermal Insulation Composite System)63

Oben