what does your contract with the prefabricated house company say about such costs?
Basically, I agree with the others. You discuss such things in advance. That the crane company obviously adds something now is legitimate. They want to earn something, have the administration, a few phone calls, etc.
If additional measures or services become necessary due to local conditions, the requirements from the soil survey, or conditions of the building permit, these are not included in our contractually agreed scope of services and must be commissioned and paid for separately. This also applies to any necessary road closures with resulting conditions.