burnatam
2019-04-29 16:23:22
- #1
Hello,
first of all, thank you very much for this forum! I read many useful posts here. Now to my question:
Unfortunately, our plot is about one meter below street level, the house itself is already planned and a construction company (GU) has also been found and signed, no basement is planned. Since we do not want to build too far below street level, the current compromise (this is also what was submitted to the building authority) is to raise the plot slightly (still below street level); the neighbors did this years ago. According to the soil survey, we have 20-30 cm of topsoil, which of course must be removed. Afterwards, we would have to fill about 50 cm (according to the soil survey, with RCL 45). A load-bearing slab will then be poured on top. The base area, +1 m on each side, of the house is about 95 m2. According to my calculation, that would be about 47.5 m3, so (according to an online calculator) about 90 tons of RCL.
My GU offers me a price of €48 per ton of RCL including delivery, compaction, etc.
Now to the questions:
- Does it even make sense to gravel up that high?
- Is the price per ton reasonable? I mean, I don’t have much choice left, but purely out of interest.
Many thanks & regards
first of all, thank you very much for this forum! I read many useful posts here. Now to my question:
Unfortunately, our plot is about one meter below street level, the house itself is already planned and a construction company (GU) has also been found and signed, no basement is planned. Since we do not want to build too far below street level, the current compromise (this is also what was submitted to the building authority) is to raise the plot slightly (still below street level); the neighbors did this years ago. According to the soil survey, we have 20-30 cm of topsoil, which of course must be removed. Afterwards, we would have to fill about 50 cm (according to the soil survey, with RCL 45). A load-bearing slab will then be poured on top. The base area, +1 m on each side, of the house is about 95 m2. According to my calculation, that would be about 47.5 m3, so (according to an online calculator) about 90 tons of RCL.
My GU offers me a price of €48 per ton of RCL including delivery, compaction, etc.
Now to the questions:
- Does it even make sense to gravel up that high?
- Is the price per ton reasonable? I mean, I don’t have much choice left, but purely out of interest.
Many thanks & regards