Ade123
2020-04-07 17:13:21
- #1
Hello, I am a bit confused because there are different statements on the internet, and the answers from contacts are also unsatisfactory. For us, 7cm EPS and 2cm impact sound insulation come on the floor slab (after that underfloor heating/screed/tiles). On the internet, it says that the edge insulation strip should only be installed at the last insulation level, so in my case after the 7cm EPS have been laid, but there are also descriptions where it is stapled from the concrete slab? Would it be wrong to lay EPS first, then the edge insulation strip, and finally the impact sound insulation? Regards