Development: Choose the location of the sewer channel

  • Erstellt am 2017-03-08 16:18:09

Bauhaus

2017-03-08 16:18:09
  • #1
Hello everyone,

in the meantime, we are proud landowners and the development is slowly taking shape. We have now learned that the sewage pipe in the west (indicated in green on the sketch) is to be connected from our cul-de-sac.

Mentally, I picture our house standing in the east to be away from the main road and so that the garden lies in the west. My idea was therefore to move the pipe further east so that the gap from the house to the pipe is smaller later on.

However, I was then made to understand that the pipe would lie higher there because it slopes from east to west. This could be relevant because we want to build with a basement and also plan a WC/shower. In the west, the pipe would be at -3.95m, further east it would be "only" (?) at -3.10 to -3.20m deep. Currently, I could still influence the location of the pipe, afterwards I have to live with it.

Should I simply leave the pipe in the west as it is? How expensive/difficult is it if you have a bigger gap? The other utilities (electricity/water) I will also leave there?

Or should I have the sewage pipe laid further into the cul-de-sac? Could the missing centimeters then later cause problems in the basement, so that I inevitably need a lifting station?

Maybe this is also important: The whole new development slopes down from south to north!

What experiences have you had with this? Unfortunately, we have not yet engaged a fixed architect/general contractor to ask. :-/

Thanks in advance.
 

wrobel

2017-03-08 17:14:28
  • #2
Good morning

Since the lowest drainage is certainly below the backwater level, a lifting system is necessary anyway. I would place the inspection shaft approximately at l.

Olli
 

Alex85

2017-03-08 19:39:22
  • #3
Where is the difference whether the channel would be extended further into the dead-end street and thus be higher or whether it ends at the marked spot, lying deeper there, but then the channel on your private property must have the necessary slope accordingly? If you have to pay for both options entirely out of your own pocket, I see no difference. A lifting system should be provided if a toilet is planned downstairs. Unfortunately probably not a bargain.
 

Bauhaus

2017-03-09 17:44:47
  • #4
Hello,

first of all, thank you for the answers.

My thought was that it would certainly be very expensive if the sewer is on the "wrong side" and then all media have to be routed "across" the property to the house.

Obviously, the costs for a few meters are probably manageable, so it hardly matters. And regarding the slope, it apparently is not a big problem either, since the sewer would still be deep enough when laid. At least, that was the information from the friendly caseworker from the city. He said that for a toilet in the basement only a backwater valve would be required.

I think I will have the connection laid in the middle and hope that it won't come back to haunt me later....
 

Alex85

2017-03-09 18:14:57
  • #5


Maybe a professional should respond to that again, but I don't believe it. How are the solids supposed to overcome gravity? You need a lifting system to lift the wastewater above the backwater level. For blackwater (toilet, toilet paper, etc.) it is a "proper" lifting system, which costs four digits. Greywater (shower water, hand basin) can be managed with a small lifting system, which costs one digit less.
 

wrobel

2017-03-09 22:07:06
  • #6


Good morning

This statement is incorrect.

Olli
 

Similar topics
25.02.2015Terrace with corner slabs (L-shape). Implementation of slope12
21.05.2016Lifting system backflow plate20
31.08.2016What slope is still comfortable?12
21.11.2016Misplanning Bavaria - slope towards house and garage - instead of away23
15.02.2017Height of the house - Backwater level - Alternatives11
27.04.2017Deep curbs for terrace construction - the slope is incorrect12
23.06.2017Change the slope of the garage roof10
09.08.2017Creating a terrace - problems with the slope18
10.10.2018Is the slope from the street to the house normal? Please provide feedback!13
05.11.2018Do we need a lifting system as the architect suggests?13
07.01.2019House with slab foundation on a slope52
07.07.2020Plot 1.5m below street level – lifting system?12
24.09.2020Insufficient slope of the sewage pipe29
29.11.2020How to construct a sloped concrete terrace?11
20.04.2021Shower slope in the wrong direction36
15.07.2021Balcony slope and waterproofing costs12
30.09.2021Slope of the garage - Which design?21
07.12.2022Terrace planning with a circular path and slight slope18
14.10.2022Defective lifting system, who pays?21
28.05.2024Water in the shaft of the lifting system19

Oben