You have either made a formal or tacit acceptance. At the latest, the construction period ends with your move-in, and no delay occurs. Anything reported as a defect afterwards is, if at all, a warranty defect. You might be able to withhold the 5,000 euros if corresponding outstanding defects from the acceptance protocol have not yet been resolved. From your builder's perspective, it is pleasing that the remaining payment is so minimal. For 5,000 euros, I would not stir any more than absolutely necessary.