Mycraft
2020-09-21 08:11:22
- #1
The law is clear on this; he is allowed to make corrections himself.
Repeat formal deadline setting, consult a lawyer. The deadline setting must not contain any errors!!! Also repeat these like reminders. Will a new plaster be applied later?The expert report is with the window installer, despite a deadline, he cannot read it, asks us how this or that is meant, comes to the house every few weeks, does a little bit here, a little bit there, but nothing complete.
That is very naive. Do you really believe that someone who delivers such work and calls it good will sit down at a table with you? Why? In their eyes, everything fits perfectly!The pictures do not look good. How was it before? Were the "wood inlays" already there before? The window maker seems willing to solve the problem and now wants to do it properly - hence the request for the measurements. It should be solvable after all. Everyone around one table and done.