Cost of two carports in the Nuremberg area

  • Erstellt am 2022-03-23 14:29:14

MisterMatze

2022-03-23 14:29:14
  • #1
Hello everyone,

we are currently at the topic of carports, after that everything on the house and property is finished.
We have an offer from a recommended carpenter.
Attention all net prices
Carport 1: 8x3.5m

Cut, deliver and assemble wood for the carport: flat rate €6200
Nail roof sheathing in tongue and groove, install counter battens: approx. 28m² at €58 = €1624
Deliver and install gutter and downpipe in titanium zinc: flat rate €950
Deliver and install trapezoidal sheet with anti-condensation coating in anthracite: 30m² at €95 = €2850
Deliver and attach wall cladding in larch as rhombus slats (only one long side): 20m² at €85 = €1700
= €13324

Carport 2: No wall cladding - otherwise like above - only with the dimensions 6x3.5m = flat rate €11500

In other words
Net: €24824
19%: €4716.56
Gross: €29540.56

I find nearly €30K for two carports a lot of money, but at the same time I have no idea if this reflects current prices or not.

The whole project would be in the Nürnberg area, Bavaria.

Thanks & regards
Matze
 

WilderSueden

2022-03-23 14:35:46
  • #2
For a carport from the carpenter, this seems relatively common to me. The solution is to order a kit and do it yourself. Then you can get it done significantly cheaper.
 

gutentag

2022-03-24 13:08:19
  • #3
But the founding is still missing.
 

gutentag

2022-03-24 13:26:56
  • #4


You should definitely get additional offers.

I wonder why roof boarding, roof battens would suffice. Why anti-condensation? A few drops of water don't hurt any car. I have neither boarding nor anti-condensation and nothing drips.

Why 3.5 * 8 m? My carport is 3 * 5 m.
 

cschiko

2022-03-24 13:28:59
  • #5
And the smaller carport seems to me, compared to the larger one, somewhat more expensive. Because the wall cladding and other items are omitted, which together amount to more than what was deducted.
 

gutentag

2022-03-24 13:46:18
  • #6
Someone probably factored in considerable room for negotiation. However, I fear profit maximization.
 
Oben