That would have to be checked again by reading the passage exactly, because 200 EUR/day is no small matter for the entrepreneur.
In my contract it also says that I get 50 EUR/day. However, it also states that everything the contractor, i.e. the general contractor, is not responsible for, does not count towards the construction time guarantee.
Drying times, for example.
It would be interesting in this context whether he can also attribute delivery bottlenecks with the material to force majeure?
I am aware that the money will be very hard to get. But the possibility exists :cool: