Domski
2019-04-22 07:32:42
- #1
It also depends heavily on local customs. With us, the [vnb] installs a new meter at each module connection, and before the electrician takes down the box, the meter is removed again. On the paper, the meter reading is then also recorded.
In fact, the electrician is not allowed to take the box before the meter is removed. In that case, it would also be theft of the meter.
I would first ask the [vnb] about who exactly owns the meter.
In fact, the electrician is not allowed to take the box before the meter is removed. In that case, it would also be theft of the meter.
I would first ask the [vnb] about who exactly owns the meter.