Construction power meter reading not recorded. Is the incorrect billing correct?

  • Erstellt am 2019-04-10 13:03:03

Domski

2019-04-22 07:32:42
  • #1
It also depends heavily on local customs. With us, the [vnb] installs a new meter at each module connection, and before the electrician takes down the box, the meter is removed again. On the paper, the meter reading is then also recorded.

In fact, the electrician is not allowed to take the box before the meter is removed. In that case, it would also be theft of the meter.

I would first ask the [vnb] about who exactly owns the meter.
 

Snowy36

2019-04-22 13:16:30
  • #2
I would talk to the person who had the meter after you ... maybe they have the meter reading from the start of construction and they should just pay the money to you instead of to the provider and that’s that
 

Similar topics
18.11.2016Electrician's invoice after 2.5 years - What are my rights?18
12.05.2017Is an advance payment to an electrician lawful?23
01.08.2019Trouble with the electrician / tolerance range?!42
20.02.2020What does the electrician do during the shell construction phase?19
23.03.2020Building law: Electrician refuses to continue78
21.07.2021Problem with the electrician - what would you do?78
09.07.2023Electrician Cost Estimate - New Installation22

Oben