Construction in the Water Protection Area - Procedure and Expected Costs

  • Erstellt am 2021-10-09 15:57:27

Filipowitsch

2021-10-09 15:57:27
  • #1
Hello dear house-building forum,

We are currently planning the purchase of a plot of land located in the water protection area Zone II. (existing development area)
The development plan defines the minimum basement floor height, which must not be undercut due to water protection aspects.

The following steps have been completed so far:
- Creation of a site and elevation plan for the plot
- initial design planning from the prefabricated house provider (including full basement)

For me, the logical next step would be the creation of a geological report to gain more cost certainty regarding the incidental construction costs.
The prefabricated house provider advises against creating the report at this point in time and instead recommends contacting an earthworks contractor. I wonder how the earthworks contractor is supposed to make a reliable cost estimate without an existing geological report...?

Therefore my first question: What further approach do you recommend at the current time?

The municipality's information sheet mentions the following necessary protective measures when building in water protection area Zone II:

- Waiver of deep building foundations (e.g., deep basements, pile foundations)
- Installation of wastewater pipes with increased requirements for tightness and regular testability
- Execution of ground pipes only outside of building areas for repair and rehabilitation cases
- Waiver of infiltration of rainwater
- Liquid-tight construction of access roads and parking spaces
- Complete collection of surface water and discharge into the sewer system (also during the construction period)
- Waiver of underground storage of water-hazardous substances (e.g., heating oil)
- Waiver of underground storage of rainwater
- Waiver of drainage systems
- Increased monitoring and special operation of vulnerable drinking water abstractions in coordination with the local water supply company (if necessary, precautionary disinfection or temporary shutdown during the construction period)

Does anyone have experience with building in a water protection area and can say something about the additional costs (both initial and ongoing) as well as additional required planning steps?

Thank you in advance and have a nice weekend!
 

11ant

2021-10-09 18:16:53
  • #2

From my point of view, one of the next logical steps would be for you to show us the site and elevation plan here. Of course, you are also welcome to share the initial design planning. You will find a whole lot of experienced advisors here, unfortunately all with cloudy crystal balls.
 

Filipowitsch

2021-10-09 19:18:23
  • #3
Thank you very much for the quick response and apologies for the missing documents. I have now attached them.






 

Similar topics
26.10.2013Planning/Architect, possible execution by "prefabricated house providers"21
27.07.2013Average construction time for a semi-detached house with a basement11
18.03.2015Developer information varies. What is the realistic construction time?19
02.06.2016Necessary insurances during construction and afterwards11
23.01.2017What to do if the construction time is not met15
27.01.2017Price-performance comparison: Which is the best prefabricated house provider?16
27.06.2018Prefabricated house provider with electrical installation as own work14
22.08.2019Who are the "most affordable & good" prefabricated house providers?13
09.10.2019Looking for affordable & good prefab house providers. (lower budget)62
13.03.2021Opinion on various prefabricated house providers desired68
23.05.2021General contractor / prefabricated house provider with an existing BG (HOAI Phase 4)27
09.07.2021Is the construction time specified in the prefabricated house contract binding?19
06.06.2023Estimation of construction time for the new build of a semi-detached house17
12.02.2024Preliminary design via the architect and then tendering?16

Oben