phill1.
2019-11-11 09:51:11
- #1
Hello, we are currently building a new house with a construction company, with a building application, drawings, structural analysis, and energy certificate included in the contract. BEFORE the contract signing, I sent him an email asking him to please check the plot of land, with a soil report attached. After the foundation slab was completed, he informed me that the slab would need to be thicker. Then an email came saying
"
We assumed that the soil conditions were normal before the contract signing, but after inspections by our structural engineer, it turned out that poor
soil conditions are present.
Due to the poor conditions, the foundations must be reinforced and the slab must be made thicker, from 18cm to 30cm.
Unfortunately, this results in additional costs of €5,600.00 including VAT, we ask you to confirm this.
In the additional cost statement it now says 5600+19 VAT....
In my building contract it says
"Foundations and slab"
Concrete and dimensions according to structural calculations. The slab is a concrete slab with appropriate insulation that complies with technical regulations. The foundation is carried out with strip foundations made of C20/C25 according to the requirements of the structural calculation. A galvanized steel strip is inserted into the foundations as foundation grounding. According to the structural analysis, a concrete slab is poured on an underlying construction foil on compacted fill sand. Further back in the contract it also states that the client (owner of the property, so me) also bears all incurred fees such as rough construction approval, TÜV, chimney sweep, as well as any additional costs for structural engineering, architect etc. incurred during construction.
Now the question is, are these additional costs justified? Do I have to pay them? Before the contract signing, he or the architect should have seen this.
The contract does not mention an 18 cm slab...
Thank you
"
We assumed that the soil conditions were normal before the contract signing, but after inspections by our structural engineer, it turned out that poor
soil conditions are present.
Due to the poor conditions, the foundations must be reinforced and the slab must be made thicker, from 18cm to 30cm.
Unfortunately, this results in additional costs of €5,600.00 including VAT, we ask you to confirm this.
In the additional cost statement it now says 5600+19 VAT....
In my building contract it says
"Foundations and slab"
Concrete and dimensions according to structural calculations. The slab is a concrete slab with appropriate insulation that complies with technical regulations. The foundation is carried out with strip foundations made of C20/C25 according to the requirements of the structural calculation. A galvanized steel strip is inserted into the foundations as foundation grounding. According to the structural analysis, a concrete slab is poured on an underlying construction foil on compacted fill sand. Further back in the contract it also states that the client (owner of the property, so me) also bears all incurred fees such as rough construction approval, TÜV, chimney sweep, as well as any additional costs for structural engineering, architect etc. incurred during construction.
Now the question is, are these additional costs justified? Do I have to pay them? Before the contract signing, he or the architect should have seen this.
The contract does not mention an 18 cm slab...
Thank you