Connection shaft for district heating as precast concrete part or cast in place?

  • Erstellt am 2017-09-06 19:46:27

Lagom

2017-09-06 19:46:27
  • #1
Hello everyone,

sometimes I feel that when I call about various things related to construction, I am the only one in the country building a house, ignorance as far as the eye can see...

I suspect I have a special problem but still hope you can give me some advice.

For the connection of the district heating, I need a 1x1x1.2m deep connection shaft in the base slab either

a) to be installed as a prefabricated part

or

b) to be poured during the base slab work or afterwards (probably the more expensive option)

For option a) I imagine that this shaft is installed by the earthworks contractor during the earthworks and gravel is compacted around it for the base slab, then the base slab is poured and that's it. Although I probably have to insulate the shaft separately to avoid thermal bridging.

For the second option, I am a bit confused about how this should work. Do you first make the base slab and leave this opening for the shaft? What happens to the compacted gravel next to it, doesn’t it get loosened?...

Maybe you have had to do something similar?
Which option should I choose with regard to tightness and reliability?
Where can you even get such shafts from?


Thanks in advance for the tips!


Regards
Robert
 

Knallkörper

2017-09-06 20:42:46
  • #2
At our site, the shaft was realized as a recess in the floor slab. The gravel can still be compacted - the shaft walls are made of shuttering blocks.
 

Lagom

2017-09-06 20:47:13
  • #3
Ok, so option c) so to speak. The shaft was not cast, but built with masonry. Were the formwork blocks also insulated on the outside and sealed with bitumen sheets?
 

Knallkörper

2017-09-06 22:39:06
  • #4
Most of the houses here are built with frost skirts made of shuttering blocks. The shaft is then built together with the frost skirt and practically costs nothing.

When the pipes were in place, the shaft was cast up to the height of the floor slab. On top of that came the bitumen membrane, insulation, screed, tiles. At that time, the screed was otherwise already finished. It is important that when welding the floor slab, a rim protrudes all around, where you can then work again when closing the shaft.
 

Similar topics
21.10.2011Floor slab insulation "Yes!" or "No!"14
18.09.2012Construction of a base slab with frost skirt but without foundation10
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
14.09.2012House financing - house, garage, and foundation slab approx. 290,000 EUR11
26.10.2012External perimeter insulation floor slab, basement mold risk11
21.11.2013Is the floor slab still possible this year?15
10.08.2015In which season of the year is it best to bring screed into the basement10
28.04.2016Order screed - plaster14
20.08.2016Base slab vs strip foundation15
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
06.10.2019Base plate with concrete core activation. What is your opinion?46
26.02.2018Insulation under reinforced concrete floor slab KFW5520
05.04.2018Water on ground slab, cause and leak unknown24
06.09.2018Ground slab on a gentle slope for a single-family house with a basement11
03.02.2019Underfloor heating in the floor slab - advantages and disadvantages?15
09.02.2019Ground slab with strip foundation and frost skirt23
17.08.2019Base plate - Reinforcement steel is sticking out12
13.05.2020Self-adhesive vinyl on screed20
11.05.2021Insulate floor slab - ceiling height is not sufficient14
22.09.2022Basement without additional flooring / cleaning floor slab34

Oben