Harakiri
2023-05-03 11:42:00
- #1
Hello everyone,
our construction project is almost finished, and we want to take care of the garden soon.
Due to the installation of our [Ringgrabenkollektor] as well as the use of the garden area for temporary storage of topsoil and other excavated material, however, our future garden is currently in a regrettable condition (see attached picture).
Basically, the topsoil has been mostly removed. Due to the [Ringgrabenkollektor], there are now also settlements/cracks that need to be evened out. Unfortunately, the topsoil was not handled very carefully during removal/storage, so not everything is certainly pure. Basically, the soil here is very clayey (slope clay).
I would like to first distribute the existing excavated material and create as even a surface as possible, especially towards the house – what cannot be distributed must then be moved in front of the house to design the front garden there.
I assume it would be advisable to sieve it during this process – should anything else be done, such as mixing in additives? Should the soil generally be dug over? Can/should I then use a lawn roller on it, or would that be counterproductive, since it was partly compacted by construction vehicles/excavators?
I would be grateful if someone had a small how-to on how to create a proper foundation from the “current” state for later use as a garden (mainly a vegetable garden, partly fruit trees, also a part natural meadow). Please formulate it for complete beginners, as to be honest, I’m not quite sure where to start.
It doesn’t necessarily have to be “quick,” theoretically we could even let it “rest” for one growing season, if that would be useful for later use.
Thank you for your time!
our construction project is almost finished, and we want to take care of the garden soon.
Due to the installation of our [Ringgrabenkollektor] as well as the use of the garden area for temporary storage of topsoil and other excavated material, however, our future garden is currently in a regrettable condition (see attached picture).
Basically, the topsoil has been mostly removed. Due to the [Ringgrabenkollektor], there are now also settlements/cracks that need to be evened out. Unfortunately, the topsoil was not handled very carefully during removal/storage, so not everything is certainly pure. Basically, the soil here is very clayey (slope clay).
I would like to first distribute the existing excavated material and create as even a surface as possible, especially towards the house – what cannot be distributed must then be moved in front of the house to design the front garden there.
I assume it would be advisable to sieve it during this process – should anything else be done, such as mixing in additives? Should the soil generally be dug over? Can/should I then use a lawn roller on it, or would that be counterproductive, since it was partly compacted by construction vehicles/excavators?
I would be grateful if someone had a small how-to on how to create a proper foundation from the “current” state for later use as a garden (mainly a vegetable garden, partly fruit trees, also a part natural meadow). Please formulate it for complete beginners, as to be honest, I’m not quite sure where to start.
It doesn’t necessarily have to be “quick,” theoretically we could even let it “rest” for one growing season, if that would be useful for later use.
Thank you for your time!