Claim additional operational costs. Until when is it possible?

  • Erstellt am 2010-12-05 18:15:24

n.luba

2010-12-05 18:15:24
  • #1
Hello,
in our new house construction, the flat roof was installed so that the slope, contrary to the construction description, faces the street side.
As a result, it is not possible for us to collect rainwater. This means that we have to use tap water for watering the outdoor area, and we also have to pay a fee to the city for the disposal of rainwater into the sewer system.
We will incur additional costs of approximately €120 per year. We would like to claim these additional costs from our developer.
For how many years can we claim this?

Best regards
n.luba
 

Bauexperte

2010-12-06 09:45:17
  • #2
Haven't you discussed this _before_ the building application, normally the drainage plans are created in parallel?

Apart from not understanding what speaks against connecting a rain barrel to the downpipe in the front area (street?), are you allowed to infiltrate or do you have to connect to the public sewer?

Kind regards
 

n.luba

2010-12-06 16:58:59
  • #3
Hello,

we have not received a drainage plan. Since the front side borders directly on the street (sidewalk) and in our case it is a mid-terrace house, we cannot set up a rain barrel here and must connect to the public sewer.

Best regards
n.luba
 

Bauexperte

2010-12-06 17:25:44
  • #4
Hello back,


The drainage application is usually prepared parallel to the building application documents and the builder receives one copy each for their records, unless otherwise agreed; it is generally submitted to the responsible municipal utilities/drainage authorities.

So it must be clarified where and above all due to whose negligence the flat roof is sloped towards the street, contrary to the agreement. I hardly believe that you will have a long-term claim for damages; perhaps a settlement in the form of an additional "bonus" or a credit is possible. But check before carefully whether you may not have signed accordingly in the building application and were therefore in agreement with the orientation.

Kind regards
 

fmjuchi

2010-12-06 22:07:59
  • #5
Hi,

I would check whether the "Grüne Tonne" is provided as an alternative to surface drainage in the drainage regulations.

A common alternative would be infiltration, but this would require part of the property area, which is certainly not generously sized.

best regards fm
 

n.luba

2010-12-07 09:25:23
  • #6


Hello,

when should I address this with my developer? Already now, or only during the final inspection?

Best regards
n.luba
 

Similar topics
03.08.2012Contract Supplement to the Construction Contract by the Developer36
24.07.2013Additional costs due to underfloor heating11
29.04.2014Combination of shed roof and flat roof14
12.06.2014Single-family house with flat roof - your opinions?15
22.05.2015Alternative to the flat roof16
27.02.2015Water on flat roof - double layers of roof sealing11
24.12.2015Single-family house, Energy Saving Ordinance 2016, developer recommends additional insulation - is it sensible?39
05.04.2016Is the KfW70 application still possible?14
14.04.2016Detached villa with "gable roof" or flat roof37
26.01.2017Satellite antenna on flat roof - installation and cable laying11
24.04.2017cost of walkable flat roof13
17.06.2017Is a penthouse allowed if the development plan requires a flat roof?15
25.06.2017Saddle or flat roof - experiences?18
30.08.2017setback floor, attic floor, gable roof, flat roof11
15.08.2018Work planning single-family house 180 sqm flat roof with basement & double garage142
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
29.10.2018Roof, flat roof, gable roof, shed roof - How much does each cost?22
02.11.2021Neighbor wants to prevent a flat roof. Exception possible according to the plan.36
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
12.09.2023Tile installation with additional costs for large format11

Oben