KSchmidtke
2018-11-24 09:24:02
- #1
Hello everyone,
we are very close to submitting our building application.
But now to the problem.
We always wanted to combine a gas heating system with something modern (e.g. gas with solar thermal or fuel cell) and KFW-55. In combination with something modern, KFW-55 is achievable (already clarified with KFW consultants).
But the construction company claims that this is not possible and we must use an air heat pump (I assume because it is simply their standard and therefore the fastest and easiest "for the construction company").
After a long back and forth, the architect responsible for the building application suggested the following: She plans to include an air heat pump in the building application (since this 100% meets the KFW-55 standards) and we first submit the building application so that there is no delay in construction (we already have a contractually fixed timeline).
In the meantime, the company will then technically calculate the gas options described above according to KFW-55; the company claims that will take a very long time and we would lose a lot of time if we wait for that.
She said that later regarding the changed heating system, one simply sends a "notification" to the building authority and that would be settled.
1) Is that true? Do they really not care about the heating system?
2) But aren’t there also problems of a different kind, e.g. with the KFW-55 application, which in theory was submitted but with a different heating system?
3) For the fuel cell, it is said that the KFW 433 application must be submitted already "BEFORE" construction begins... but that does not mean "with the building application," right?
Thanks in advance!
Greetings
Kerstin
we are very close to submitting our building application.
But now to the problem.
We always wanted to combine a gas heating system with something modern (e.g. gas with solar thermal or fuel cell) and KFW-55. In combination with something modern, KFW-55 is achievable (already clarified with KFW consultants).
But the construction company claims that this is not possible and we must use an air heat pump (I assume because it is simply their standard and therefore the fastest and easiest "for the construction company").
After a long back and forth, the architect responsible for the building application suggested the following: She plans to include an air heat pump in the building application (since this 100% meets the KFW-55 standards) and we first submit the building application so that there is no delay in construction (we already have a contractually fixed timeline).
In the meantime, the company will then technically calculate the gas options described above according to KFW-55; the company claims that will take a very long time and we would lose a lot of time if we wait for that.
She said that later regarding the changed heating system, one simply sends a "notification" to the building authority and that would be settled.
1) Is that true? Do they really not care about the heating system?
2) But aren’t there also problems of a different kind, e.g. with the KFW-55 application, which in theory was submitted but with a different heating system?
3) For the fuel cell, it is said that the KFW 433 application must be submitted already "BEFORE" construction begins... but that does not mean "with the building application," right?
Thanks in advance!
Greetings
Kerstin