Can the move-in be postponed due to defect remediation by BT?

  • Erstellt am 2016-05-16 09:40:56

Otus11

2016-05-18 10:31:17
  • #1
Yes, as the construction expert wrote, we are groping in the dark without a contract... That is, if you do not shy away from effort and costs, anyway a case for legal advice and not for a forum.

And handover (= actual transfer of possession, e.g. handing over keys) and acceptance (= legal approval of the completed work) are also not the same.

If now the "BT" voluntarily offered the "handover" / move-in date early by e-mail (!), that is initially only a unilateral amendment offer of the contract concluded by both parties (which provided for completion 2 months later), which without your consent, more precisely: without a contract amendment, is not that simple. Keyword: requirement of written form for contract amendment; e-mail is not written form... (implied consent is also not enough, not even "Great, we save rent, already terminated the apartment on a whim..."). What does the contract say about this, which still applies without a (formally) effective amendment?

Furthermore, the presumably greatest defect (= alleged thermal bridge) is in the common property, not in the separate property. When will the common property be accepted? By whom? (certainly not by the expert, who can at most recommend the acceptance declaration (!) -> to the person responsible for this under condominium law - which is typically the community of apartment owners (here it is disputed when this exists before handover, but then who selects the expert? And when?), possibly represented by the condominium manager.

Moreover: Only the contractor can demand acceptance; you, on the other hand - depending on the contract - have a claim to performance / completion and ideally by a date X, after which delay may occur or, if there is no date, delay must first be triggered by reminder and unsuccessful setting of a deadline. And only then may there be a claim for damages as a consequence of delay, but see my critical remarks above.

The counter-right to the acceptance demand of the contractor is the buyer's refusal to accept in case of serious defects. Without concrete delay no compensation for a concrete delay (consequence) damage.

Anyway: The most important thing is that in an acceptance (declaration) in the protocol, the rights to remedy defects continue to be reserved!

Otherwise, the legal consequence of § 640 II Construction Code applies, which leads to the loss of defect rights despite knowledge of defects in case of unconditional acceptance (despite performance of defects in the protocol!).

So familiarize yourselves with acceptance and handover in construction law, presumably according to the Construction Code (VOB/B is different!).
 

Similar topics
03.07.2023Construction supervision by an expert?17
19.02.2015Development costs §127 Building Code12
22.09.2015Building Code - Developer Contract - Postponement of Contractual Handover Date14
26.10.2015Have the house inspected by a professional / expert?12
15.10.2019Questions on the interpretation of § 34 Building Code59
14.04.2020Security deposit according to §650 of the Building Code20
06.05.2020Liberation § 31 Building Code: Roof pitch, roof shape, roof structures15
10.04.2021Delays with the general contractor, no deadline set according to § 650 Building Code65
21.08.2021§34 Building Code: Building Window and Garage21
29.12.2022Special right of termination according to § 489 Building Code - Refunds15
25.12.2023Behavior in case of imminent delay by the property developer48

Oben